Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2013 |
Principal Product | Egg Processing |
NAICS | 311999 - All Other Miscellaneous Food Manufacturing |
SIC | 2015 - Poultry Slaughtering And Processing |
Sales | $10,000,000-$50,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 31,600 |
Annual Production | 1,700,000 Units |
Production Hrs. Annual | 4,160 |
Location (State) | AR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $138,779 | 2,682,583 | kWh | $0.05 |
Electricity Demand | $54,257 | 7,462 | kW-months/year | $7.27 |
Natural Gas | $92,105 | 14,630 | MMBtu | $6.30 |
TOTAL ENERGY COSTS | $381,527 | |||
RECOMMENDED SAVINGS* | $31,575 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,341 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Administrative Changes | Electricity Usage | Electricity Demand | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $8,384 Cost: - |
- | - | - | - | $8,384 | - |
- - kWh |
- - kW-months/year |
$8,384 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,957 Cost: - |
$1,957 | 37,858 | - | - | - | - |
$1,957 37,858 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $1,212 Cost: $2,500 |
$828 | 16,016 | $384 | 53 | - | - |
$828 16,016 kWh |
$384 53 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3113 MAKE ICE DURING OFF PEAK HOURS FOR COOLING |
Savings: $20,022 Cost: $105,120 |
- | - | $20,022 | 2,754 | - | - |
- - kWh |
$20,022 2,754 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $31,575 Cost: $107,620 |
$2,785 | 53,874 | $20,406 | 2,807 | $8,384 | - | $2,785 53,874 kWh |
$20,406 2,807 kW-months/year |
$8,384 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,341 Cost: - |
$1,957 | 37,858 | - | - | $8,384 | - | $1,957 37,858 kWh |
- - kW-months/year |
$8,384 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Administrative Changes | Electricity Usage | Electricity Demand | Administrative Changes |