Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2021 |
Principal Product | Potable water |
NAICS | 221310 - Water Supply and Irrigation Systems |
SIC | 4941 - Water Supply |
Sales | $100,000,000-$500,000,000 |
# of Employees | 26 |
Plant Area (Sq.Ft.) | 115,960 |
Annual Production | 21,170,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $682,150 | 27,286,000 | kWh | $0.03 |
Electricity Demand | $276,258 | 51,349 | kW-months/year | $5.38 |
Electricity Fees | $3,360 | - | $ | - |
Natural Gas | $9,916 | 3,158 | MMBtu | $3.14 |
TOTAL ENERGY COSTS | $971,684 | |||
RECOMMENDED SAVINGS* | $25,997 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Usage | Electricity Usage | Natural Gas | Water Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $563 Cost: $1,944 |
$563 | 22,524 | - | - | - | - |
$563 22,524 kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.4153 USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER |
Savings: $24,443 Cost: $2,171 |
- | - | - | - | $24,443 | 4,362 |
- - kWh |
- - MMBtu |
$24,443 4,362 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $991 Cost: - |
$341 | 13,644 | $650 | 207 | - | - |
$341 13,644 kWh |
$650 207 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,997 Cost: $4,115 |
$904 | 36,168 | $650 | 207 | $24,443 | 4,362 | $904 36,168 kWh |
$650 207 MMBtu |
$24,443 4,362 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Usage | Electricity Usage | Natural Gas | Water Usage |