IAC Assessment: OR0326
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0326
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1998
Principal Product Auto Accessories
NAICS n/a
SIC 3714 - Motor Vehicle Parts And Accessories
Sales $50,000,000-$100,000,000
# of Employees 250
Plant Area (Sq.Ft.) 270,000
Annual Production 0 Units
Production Hrs. Annual 4,800
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $144,930 4,024,912 kWh $0.04
Electricity Demand $50,366 12,403 kW-months/year $4.06
Electricity Fees $2,450 - $ -
Natural Gas $34,335 7,865 MMBtu $4.37
TOTAL ENERGY COSTS $293,646
RECOMMENDED SAVINGS* $69,118 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $26,439
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (haz) Administrative Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (haz) Administrative Changes
$ kWh $ kW-months/year $ $ $ MMBtu $ gal $ $
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$27,520
Cost:
$83,400
$18,460 523,154 $12,700 2,953 - - $(-3,640) (-892) - - - - $18,460
523,154
kWh
$12,700
2,953
kW-months/year
-
-
$
$(-3,640)
(-892)
MMBtu
-
-
gal
-
-
$
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$6,000
Cost:
-
$6,000 169,988 - - - - - - - - - - $6,000
169,988
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,653
Cost:
$1,000
$1,974 55,979 $679 158 - - - - - - - - $1,974
55,979
kWh
$679
158
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
$
04: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$2,856
Cost:
$1,210
$2,136 60,668 $720 167 - - - - - - - - $2,136
60,668
kWh
$720
167
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
$
05: 2.1133 ADJUST BURNERS FOR EFFICIENT OPERATION Savings:
$1,680
Cost:
$405
- - - - - - $1,680 412 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$1,680
412
MMBtu
-
-
gal
-
-
$
06: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,559
Cost:
$10,400
- - - - $1,559 - - - - - - - -
-
kWh
-
-
kW-months/year
$1,559
-
$
-
-
MMBtu
-
-
gal
-
-
$
07: 3.3133 USE OTHER WASTE CONCENTRATION METHODS Savings:
$20,930
Cost:
$13,295
- - - - - - - - $17,930 68,950 $3,000 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$17,930
68,950
gal
$3,000
-
$
08: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$5,920
Cost:
$3,680
- - - - - - - - - - $5,920 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
$5,920
-
$
TOTAL RECOMMENDED Savings:
$69,118
Cost:
$113,390
$28,570 809,789 $14,099 3,278 $1,559 - $(-1,960) (-480) $17,930 68,950 $8,920 - $28,570
809,789
kWh
$14,099
3,278
kW-months/year
$1,559
-
$
$(-1,960)
(-480)
MMBtu
$17,930
68,950
gal
$8,920
-
$
TOTAL IMPLEMENTED Savings:
$26,439
Cost:
$15,505
$4,110 116,647 $1,399 325 - - - - $17,930 68,950 $3,000 - $4,110
116,647
kWh
$1,399
325
kW-months/year
-
-
$
-
-
MMBtu
$17,930
68,950
gal
$3,000
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ gal $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (haz) Administrative Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (haz) Administrative Changes