IAC logo
IAC Assessment: OR0339
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0339
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1999
Principal Product Travel Trailers
NAICS n/a
SIC 3792 - Travel Trailers And Campers
Sales $10,000,000-$50,000,000
# of Employees 200
Plant Area (Sq.Ft.) 67,000
Annual Production 765 Pieces
Production Hrs. Annual 2,040
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $22,037 868,992 kWh $0.03
Electricity Demand $15,377 44,208 kW-months/year $0.35
Electricity Fees $745 - $ -
Natural Gas $23,102 4,053 MMBtu $5.70
TOTAL ENERGY COSTS $83,546
RECOMMENDED SAVINGS* $5,119,267 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $11,492
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Increase in Production Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Increase in Production
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $ $ %
01: 4.4230 MOVE PRODUCT USING MECHANICAL MEANS Savings:
$5,106,400
Cost:
$556,000
- - - - - - - - - - - - $5,106,400 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
$5,106,400
-
%
02: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$6,650
Cost:
$24,750
$(-20) (-879) $(-690) (-144) - - $7,360 - - - - - - - $(-20)
(-879)
kWh
$(-690)
(-144)
kW-months/year
-
-
MMBtu
$7,360
-
lb
-
-
$
-
-
$
-
-
%
03: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT Savings:
$3,080
Cost:
$13,800
$2,340 106,975 $740 1,858 - - - - - - - - - - $2,340
106,975
kWh
$740
1,858
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
%
04: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$178
Cost:
-
$145 6,741 - - - - - - $15 - $18 - - - $145
6,741
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$15
-
$
$18
-
$
-
-
%
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$730
Cost:
$381
- - - - $730 128 - - - - - - - - -
-
kWh
-
-
kW-months/year
$730
128
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
%
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$254
Cost:
$1,000
$118 5,569 $136 29 - - - - - - - - - - $118
5,569
kWh
$136
29
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
%
07: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$1,508
Cost:
$1,454
$701 32,239 $807 168 - - - - - - - - - - $701
32,239
kWh
$807
168
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
%
08: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$467
Cost:
$441
$225 10,258 $242 50 - - - - - - - - - - $225
10,258
kWh
$242
50
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
%
TOTAL RECOMMENDED Savings:
$5,119,267
Cost:
$597,826
$3,509 160,903 $1,235 1,961 $730 128 $7,360 - $15 - $18 - $5,106,400 - $3,509
160,903
kWh
$1,235
1,961
kW-months/year
$730
128
MMBtu
$7,360
-
lb
$15
-
$
$18
-
$
$5,106,400
-
%
TOTAL IMPLEMENTED Savings:
$11,492
Cost:
$41,004
$3,139 143,904 $993 1,911 - - $7,360 - - - - - - - $3,139
143,904
kWh
$993
1,911
kW-months/year
-
-
MMBtu
$7,360
-
lb
-
-
$
-
-
$
-
-
%
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $ $ %
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Increase in Production Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Increase in Production