Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1999 |
Principal Product | Model train cars |
NAICS | n/a |
SIC | 3944 - Games, Toys, and Children's Vehicles, Except Dolls and Bicycles |
Sales | $1,000,000-$5,000,000 |
# of Employees | 87 |
Plant Area (Sq.Ft.) | 33,000 |
Annual Production | 320,000 Pieces |
Production Hrs. Annual | 2,032 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $16,757 | 491,794 | kWh | $0.03 |
Electricity Demand | $7,031 | 31,248 | kW-months/year | $0.23 |
Electricity Fees | $4,114 | - | $ | - |
Natural Gas | $3,762 | 767 | MMBtu | $4.90 |
TOTAL ENERGY COSTS | $33,670 | |||
RECOMMENDED SAVINGS* | $436,624 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $82,500 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Other Liquid (haz) | Personnel Changes | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Other Liquid (haz) | Personnel Changes | Ancillary Material Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | gal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.446 AUTOMATE FINISHING PROCESS |
Savings: $290,000 Cost: $165,000 |
- | - | - | - | - | - | - | - | $290,000 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - gal |
$290,000 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.421 MODIFY CURRENT INCENTIVE PROGRAM |
Savings: $45,000 Cost: $23,000 |
- | - | - | - | - | - | - | - | $45,000 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - gal |
$45,000 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.446 AUTOMATE FINISHING PROCESS |
Savings: $39,300 Cost: $32,000 |
- | - | - | - | - | - | - | - | $39,300 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - gal |
$39,300 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $37,500 Cost: $50,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $37,500 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - gal |
- - $ |
- - $ |
$37,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.425 ELIMINATE/REDUCE REDUNDANT INSPECTIONS |
Savings: $17,775 Cost: $250 |
- | - | - | - | - | - | - | - | $17,775 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - gal |
$17,775 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $1,746 Cost: - |
$1,111 | 32,825 | $635 | 172 | - | - | - | - | - | - | - | - | - | - |
$1,111 32,825 kWh |
$635 172 kW-months/year |
- - $ |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $403 Cost: - |
$256 | 7,620 | $147 | 40 | - | - | - | - | - | - | - | - | - | - |
$256 7,620 kWh |
$147 40 kW-months/year |
- - $ |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $360 Cost: $1,000 |
- | - | - | - | $360 | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$360 - $ |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.8143 RECYCLE CLEANING SOLVENT AND REUSE |
Savings: $4,540 Cost: $6,000 |
- | - | - | - | - | - | $1,750 | 385 | - | - | $2,790 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,750 385 gal |
- - $ |
$2,790 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $436,624 Cost: $277,250 |
$1,367 | 40,445 | $782 | 212 | $360 | - | $1,750 | 385 | $392,075 | - | $2,790 | - | $37,500 | - | $1,367 40,445 kWh |
$782 212 kW-months/year |
$360 - $ |
$1,750 385 gal |
$392,075 - $ |
$2,790 - $ |
$37,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $82,500 Cost: $73,000 |
- | - | - | - | - | - | - | - | $45,000 | - | - | - | $37,500 | - | - - kWh |
- - kW-months/year |
- - $ |
- - gal |
$45,000 - $ |
- - $ |
$37,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | gal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Other Liquid (haz) | Personnel Changes | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Other Liquid (haz) | Personnel Changes | Ancillary Material Cost | Primary Product |