IAC logo
IAC Assessment: OR0344
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0344
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1999
Principal Product Wood Furniture
NAICS n/a
SIC 2511 - Wood Household Furniture
Sales $5,000,000-$10,000,000
# of Employees 140
Plant Area (Sq.Ft.) 43,500
Annual Production 2,583,000 Thousand Feet
Production Hrs. Annual 4,750
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $78,104 2,332,943 kWh $0.03
Electricity Demand $20,347 77,628 kW-months/year $0.26
Electricity Fees $10,286 - $ -
Natural Gas $9,906 2,094 MMBtu $4.73
TOTAL ENERGY COSTS $136,217
RECOMMENDED SAVINGS* $168,788 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $45,746
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Personnel Changes Electricity Usage Electricity Demand Electricity Fees Personnel Changes
$ kWh $ kW-months/year $ $ $ $
01: 4.421 MODIFY CURRENT INCENTIVE PROGRAM Savings:
$94,000
Cost:
$23,300
- - - - - - $94,000 - -
-
kWh
-
-
kW-months/year
-
-
$
$94,000
-
$
02: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$35,970
Cost:
$40,000
- - $(-530) (-164) - - $36,500 - -
-
kWh
$(-530)
(-164)
kW-months/year
-
-
$
$36,500
-
$
03: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$7,100
Cost:
$6,920
- - - - - - $7,100 - -
-
kWh
-
-
kW-months/year
-
-
$
$7,100
-
$
04: 4.421 MODIFY CURRENT INCENTIVE PROGRAM Savings:
$6,490
Cost:
$6,300
- - - - - - $6,490 - -
-
kWh
-
-
kW-months/year
-
-
$
$6,490
-
$
05: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$9,200
Cost:
$22,400
$7,360 216,589 $1,840 576 - - - - $7,360
216,589
kWh
$1,840
576
kW-months/year
-
-
$
-
-
$
06: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,915
Cost:
$5,400
- - - - $1,915 - - - -
-
kWh
-
-
kW-months/year
$1,915
-
$
-
-
$
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,286
Cost:
$1,000
$2,655 77,960 $631 197 - - - - $2,655
77,960
kWh
$631
197
kW-months/year
-
-
$
-
-
$
08: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$10,827
Cost:
$1,210
$8,810 259,086 $2,017 630 - - - - $8,810
259,086
kWh
$2,017
630
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$168,788
Cost:
$106,530
$18,825 553,635 $3,958 1,239 $1,915 - $144,090 - $18,825
553,635
kWh
$3,958
1,239
kW-months/year
$1,915
-
$
$144,090
-
$
TOTAL IMPLEMENTED Savings:
$45,746
Cost:
$47,300
$2,655 77,960 $101 33 - - $42,990 - $2,655
77,960
kWh
$101
33
kW-months/year
-
-
$
$42,990
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Personnel Changes Electricity Usage Electricity Demand Electricity Fees Personnel Changes