Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2001 |
Principal Product | Specialty SMT Products |
NAICS | n/a |
SIC | 3672 - Printed Circuit Boards |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 32,000 |
Annual Production | 72,000 Pieces |
Production Hrs. Annual | 6,032 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $53,693 | 1,312,720 | kWh | $0.04 |
Electricity Demand | $9,720 | 39,252 | kW-months/year | $0.25 |
Electricity Fees | $948 | - | $ | - |
Natural Gas | $4,882 | 655 | MMBtu | $7.45 |
TOTAL ENERGY COSTS | $69,243 | |||
RECOMMENDED SAVINGS* | $956,872 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $955,025 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Ancillary Material Cost | Primary Product | Increase in Production | Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Ancillary Material Cost | Primary Product | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $187,500 Cost: $18,000 |
- | - | - | - | - | - | - | - | - | - | $187,500 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
$187,500 - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $290,325 Cost: $250,000 |
- | - | - | - | - | - | - | - | $(-4,985) | - | - | - | $295,310 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$(-4,985) - $ |
- - $ |
$295,310 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $108,900 Cost: $60,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $108,900 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
$108,900 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.421 MODIFY CURRENT INCENTIVE PROGRAM |
Savings: $368,300 Cost: $29,120 |
- | - | - | - | - | - | $368,300 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$368,300 - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8112 COMBINE UTILITY METERS |
Savings: $1,079 Cost: $3,000 |
- | - | $(-2,525) | - | $3,604 | - | - | - | - | - | - | - | - | - |
- - kWh |
$(-2,525) - kW-months/year |
$3,604 - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $768 Cost: - |
$647 | 15,819 | $121 | 25 | - | - | - | - | - | - | - | - | - | - |
$647 15,819 kWh |
$121 25 kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $956,872 Cost: $360,120 |
$647 | 15,819 | $(-2,404) | 25 | $3,604 | - | $368,300 | - | $(-4,985) | - | $187,500 | - | $404,210 | - | $647 15,819 kWh |
$(-2,404) 25 kW-months/year |
$3,604 - $ |
$368,300 - $ |
$(-4,985) - $ |
$187,500 - $ |
$404,210 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $955,025 Cost: $357,120 |
- | - | - | - | - | - | $368,300 | - | $(-4,985) | - | $187,500 | - | $404,210 | - | - - kWh |
- - kW-months/year |
- - $ |
$368,300 - $ |
$(-4,985) - $ |
$187,500 - $ |
$404,210 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Ancillary Material Cost | Primary Product | Increase in Production | Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Ancillary Material Cost | Primary Product | Increase in Production |