Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2005 |
Principal Product | Potato and corn chips |
NAICS | 311919 - Other Snack Food Manufacturing |
SIC | 2096 - Potato Chips And Similar Snacks |
Sales | $50,000,000-$100,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 300,000 |
Annual Production | 18,000,000 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $715,158 | 17,008,350 | kWh | $0.04 |
Electricity Demand | $181,519 | 390,348 | kW-months/year | $0.47 |
Electricity Fees | $2,088 | - | $ | - |
Natural Gas | $1,000,000 | 357,286 | MMBtu | $2.80 |
TOTAL ENERGY COSTS | $2,275,588 | |||
RECOMMENDED SAVINGS* | $67,670 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $25,000 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Administrative Changes | Electricity Usage | Electricity Demand | Electricity Fees | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $32,471 Cost: - |
$27,022 | 643,131 | $5,449 | 82 | - | - | - | - |
$27,022 643,131 kWh |
$5,449 82 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $2,880 Cost: $300 |
$2,880 | 72,000 | - | - | - | - | - | - |
$2,880 72,000 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $25,000 Cost: $26,000 |
- | - | - | - | - | - | $25,000 | - |
- - kWh |
- - kW-months/year |
- - $ |
$25,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $7,319 Cost: $8,000 |
- | - | - | - | $7,319 | - | - | - |
- - kWh |
- - kW-months/year |
$7,319 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $67,670 Cost: $34,300 |
$29,902 | 715,131 | $5,449 | 82 | $7,319 | - | $25,000 | - | $29,902 715,131 kWh |
$5,449 82 kW-months/year |
$7,319 - $ |
$25,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $25,000 Cost: $26,000 |
- | - | - | - | - | - | $25,000 | - | - - kWh |
- - kW-months/year |
- - $ |
$25,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Administrative Changes | Electricity Usage | Electricity Demand | Electricity Fees | Administrative Changes |