Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2005 |
Principal Product | Coffee Syrups & Sauces |
NAICS | 311920 - Coffee and Tea Manufacturing |
SIC | 2087 - Flavoring Extracts And Syrups, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 65,000 |
Annual Production | 4,500,000 Pieces |
Production Hrs. Annual | 2,000 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $61,990 | 1,066,960 | kWh | $0.06 |
Electricity Demand | $3,909 | 3,795 | kW-months/year | $1.03 |
Electricity Fees | $1,282 | - | $ | - |
Natural Gas | $59,021 | 6,916 | MMBtu | $8.53 |
TOTAL ENERGY COSTS | $189,365 | |||
RECOMMENDED SAVINGS* | $162,695 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $157,564 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Other Gas | Administrative Changes | Electricity Usage | Natural Gas | Other Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $21,624 Cost: - |
- | - | - | - | - | - | $21,624 | - |
- - kWh |
- - MMBtu |
- - MMBtu |
$21,624 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $24,290 Cost: $4,400 |
$590 | 9,300 | $1,300 | 270 | - | - | $22,400 | - |
$590 9,300 kWh |
$1,300 270 MMBtu |
- - MMBtu |
$22,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $21,300 Cost: $5,100 |
- | - | - | - | - | - | $21,300 | - |
- - kWh |
- - MMBtu |
- - MMBtu |
$21,300 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.514 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS |
Savings: $8,960 Cost: $3,000 |
- | - | - | - | - | - | $8,960 | - |
- - kWh |
- - MMBtu |
- - MMBtu |
$8,960 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3414 BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT |
Savings: $41,000 Cost: $69,000 |
- | - | - | - | - | - | $41,000 | - |
- - kWh |
- - MMBtu |
- - MMBtu |
$41,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS |
Savings: $40,390 Cost: $72,000 |
- | - | - | - | $2,590 | 138 | $37,800 | - |
- - kWh |
- - MMBtu |
$2,590 138 MMBtu |
$37,800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2192 USE HEAT EXCHANGE FLUIDS INSTEAD OF STEAM IN PIPELINE TRACING SYSTEMS |
Savings: $5,131 Cost: $15,000 |
- | - | $5,131 | 5,554 | - | - | - | - |
- - kWh |
$5,131 5,554 MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $162,695 Cost: $168,500 |
$590 | 9,300 | $6,431 | 5,824 | $2,590 | 138 | $153,084 | - | $590 9,300 kWh |
$6,431 5,824 MMBtu |
$2,590 138 MMBtu |
$153,084 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $157,564 Cost: $153,500 |
$590 | 9,300 | $1,300 | 270 | $2,590 | 138 | $153,084 | - | $590 9,300 kWh |
$1,300 270 MMBtu |
$2,590 138 MMBtu |
$153,084 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Other Gas | Administrative Changes | Electricity Usage | Natural Gas | Other Gas | Administrative Changes |