IAC Assessment: OR0580
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0580
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2012
Principal Product Packages
NAICS 561910 - Packaging and Labeling Services
SIC 7389 - Business Services, Nec
Sales $5,000,000-$10,000,000
# of Employees 120
Plant Area (Sq.Ft.) 100,000
Annual Production 100,000 Units
Production Hrs. Annual 2,690
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $31,082 335,476 kWh $0.09
Electricity Demand $2,218 421 kW-months/year $5.27
Electricity Fees $2,396 - $ -
Natural Gas $31,625 3,283 MMBtu $9.63
TOTAL ENERGY COSTS $67,321
RECOMMENDED SAVINGS* $18,798 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $16,829
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$12,485
Cost:
$850
- - - - $12,485 1,232 - - - - - - -
-
kWh
-
-
kW-months/year
$12,485
1,232
MMBtu
-
-
lb
-
-
$
-
-
$
02: 3.1161 ELIMINATE/REDUCE AN OPERATION Savings:
$3,906
Cost:
$14,500
$(-84) (-1,155) $(-701) (-146) - - $4,691 5 - - - - $(-84)
(-1,155)
kWh
$(-701)
(-146)
kW-months/year
-
-
MMBtu
$4,691
5
lb
-
-
$
-
-
$
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$438
Cost:
$555
$368 3,470 - - - - - - $39 - $31 - $368
3,470
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$39
-
$
$31
-
$
04: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$1,969
Cost:
$29,164
$1,930 27,100 $39 8 - - - - - - - - $1,930
27,100
kWh
$39
8
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$18,798
Cost:
$45,069
$2,214 29,415 $(-662) (-138) $12,485 1,232 $4,691 5 $39 - $31 - $2,214
29,415
kWh
$(-662)
(-138)
kW-months/year
$12,485
1,232
MMBtu
$4,691
5
lb
$39
-
$
$31
-
$
TOTAL IMPLEMENTED Savings:
$16,829
Cost:
$15,905
$284 2,315 $(-701) (-146) $12,485 1,232 $4,691 5 $39 - $31 - $284
2,315
kWh
$(-701)
(-146)
kW-months/year
$12,485
1,232
MMBtu
$4,691
5
lb
$39
-
$
$31
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Administrative Changes Ancillary Material Cost