Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2013 |
Principal Product | Breakfast Cereal |
NAICS | 311230 - Breakfast Cereal Manufacturing |
SIC | 2043 - Cereal Breakfast Foods |
Sales | $5,000,000-$10,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 122,000 |
Annual Production | 875,000 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $255,459 | 4,467,896 | kWh | $0.06 |
Electricity Demand | $87,474 | 13,775 | kW-months/year | $6.35 |
Electricity Fees | $9,798 | - | $ | - |
Natural Gas | $220,784 | 40,266 | MMBtu | $5.48 |
LPG | $26,637 | 1,037 | MMBtu | $25.69 |
TOTAL ENERGY COSTS | $754,889 | |||
RECOMMENDED SAVINGS* | $28,221 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,881 Cost: $3,300 |
$1,993 | 35,412 | $888 | 137 | - | - | - | - | - | - |
$1,993 35,412 kWh |
$888 137 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.454 MODIFY STARTUP/SHUTDOWN TIMES |
Savings: $10,380 Cost: $800 |
$10,380 | 184,405 | - | - | - | - | - | - | - | - |
$10,380 184,405 kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $977 Cost: $1,975 |
$808 | 12,784 | - | - | - | - | $87 | - | $82 | - |
$808 12,784 kWh |
- - kW-months/year |
- - $ |
$87 - $ |
$82 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.7212 IMPROVED MATERIAL HANDLING (MIXING AND TRANSFER) |
Savings: $9,796 Cost: $50,179 |
$(-605) | (-10,742) | $(-767) | (-118) | $12,168 | - | $(-1,000) | - | - | - |
$(-605) (-10,742) kWh |
$(-767) (-118) kW-months/year |
$12,168 - $ |
$(-1,000) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $4,187 Cost: $2,283 |
$3,427 | 60,882 | $760 | 117 | - | - | - | - | - | - |
$3,427 60,882 kWh |
$760 117 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,221 Cost: $58,537 |
$16,003 | 282,741 | $881 | 136 | $12,168 | - | $(-913) | - | $82 | - | $16,003 282,741 kWh |
$881 136 kW-months/year |
$12,168 - $ |
$(-913) - $ |
$82 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost |