Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2015 |
Principal Product | Treated Water |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | $5,000,000-$10,000,000 |
# of Employees | 10 |
Plant Area (Sq.Ft.) | 830,000 |
Annual Production | 71,000,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $223,929 | 4,227,000 | kWh | $0.05 |
Electricity Demand | $105,172 | 11,352 | kW-months/year | $9.26 |
Electricity Fees | $17,833 | - | $ | - |
Natural Gas | $10,192 | 701 | MMBtu | $14.54 |
TOTAL ENERGY COSTS | $357,126 | |||
RECOMMENDED SAVINGS* | $48,816 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $18,899 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $16,127 Cost: $9,607 |
$13,478 | 244,390 | $2,649 | 336 | - | - | - | - |
$13,478 244,390 kWh |
$2,649 336 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $25,082 Cost: $17,274 |
$25,082 | 454,800 | - | - | - | - | - | - |
$25,082 454,800 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $2,772 Cost: $50 |
- | - | - | - | $2,772 | - | - | - |
- - kWh |
- - kW-months/year |
$2,772 - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,835 Cost: $9,332 |
$7,375 | 133,726 | - | - | - | - | $(-2,540) | - |
$7,375 133,726 kWh |
- - kW-months/year |
- - MMBtu |
$(-2,540) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $48,816 Cost: $36,263 |
$45,935 | 832,916 | $2,649 | 336 | $2,772 | - | $(-2,540) | - | $45,935 832,916 kWh |
$2,649 336 kW-months/year |
$2,772 - MMBtu |
$(-2,540) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $18,899 Cost: $9,657 |
$13,478 | 244,390 | $2,649 | 336 | $2,772 | - | - | - | $13,478 244,390 kWh |
$2,649 336 kW-months/year |
$2,772 - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |