Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2015 |
Principal Product | Smoked Seafood |
NAICS | 311710 - Seafood Product Preparation and Packaging |
SIC | 2092 - Fresh Or Frozen Prepared Fish |
Sales | $50,000,000-$100,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 95,000 |
Annual Production | 6,000,000 Units |
Production Hrs. Annual | 6,240 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $156,434 | 3,107,161 | kWh | $0.05 |
Electricity Demand | $22,269 | 5,392 | kW-months/year | $4.13 |
Electricity Fees | $75,132 | - | $ | - |
Natural Gas | $185,245 | 17,851 | MMBtu | $10.38 |
TOTAL ENERGY COSTS | $439,080 | |||
RECOMMENDED SAVINGS* | $143,235 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $54,240 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT |
Savings: $52,251 Cost: $18,807 |
$3,136 | 45,765 | - | - | - | - | $49,115 | - |
$3,136 45,765 kWh |
- - kW-months/year |
- - MMBtu |
$49,115 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL |
Savings: $76,637 Cost: $205,256 |
$69,345 | 1,012,047 | $7,292 | 1,766 | - | - | - | - |
$69,345 1,012,047 kWh |
$7,292 1,766 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,989 Cost: $170 |
- | - | - | - | $1,989 | 192 | - | - |
- - kWh |
- - kW-months/year |
$1,989 192 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $10,575 Cost: $3,600 |
$10,575 | 154,339 | - | - | - | - | - | - |
$10,575 154,339 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,783 Cost: $2,340 |
$1,783 | 26,028 | - | - | - | - | - | - |
$1,783 26,028 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $143,235 Cost: $230,173 |
$84,839 | 1,238,179 | $7,292 | 1,766 | $1,989 | 192 | $49,115 | - | $84,839 1,238,179 kWh |
$7,292 1,766 kW-months/year |
$1,989 192 MMBtu |
$49,115 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $54,240 Cost: $18,977 |
$3,136 | 45,765 | - | - | $1,989 | 192 | $49,115 | - | $3,136 45,765 kWh |
- - kW-months/year |
$1,989 192 MMBtu |
$49,115 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |