IAC Assessment: OR0688
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0688
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2017
Principal Product Printing
NAICS 322212 - Folding Paperboard Box Manufacturing
SIC 2657 - Folding Paperboard Boxes
Sales $10,000,000-$50,000,000
# of Employees 60
Plant Area (Sq.Ft.) 96,515
Annual Production 108,000,000 Units
Production Hrs. Annual 6,240
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $178,884 2,104,520 kWh $0.08
Electricity Demand $1 6,239 kW-months/year $0.00
Electricity Fees $12,075 - $ -
Natural Gas $86,421 13,186 MMBtu $6.55
TOTAL ENERGY COSTS $277,381
RECOMMENDED SAVINGS* $36,866 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $12,652
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$3,431
Cost:
$448
- - - - $3,431 506 -
-
kWh
-
-
kW-months/year
$3,431
506
MMBtu
02: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$9,221
Cost:
$180,000
$4,928 57,978 - - $4,293 655 $4,928
57,978
kWh
-
-
kW-months/year
$4,293
655
MMBtu
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$3,049
Cost:
-
$3,049 35,873 - - - - $3,049
35,873
kWh
-
-
kW-months/year
-
-
MMBtu
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$21,165
Cost:
-
$21,164 248,991 $1 824 - - $21,164
248,991
kWh
$1
824
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$36,866
Cost:
$180,448
$29,141 342,842 $1 824 $7,724 1,161 $29,141
342,842
kWh
$1
824
kW-months/year
$7,724
1,161
MMBtu
TOTAL IMPLEMENTED Savings:
$12,652
Cost:
$180,448
$4,928 57,978 - - $7,724 1,161 $4,928
57,978
kWh
-
-
kW-months/year
$7,724
1,161
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas