Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2018 |
Principal Product | Formaldehyde resins and adhesives |
NAICS | 325211 - Plastics Material and Resin Manufacturing |
SIC | 2821 - Plastics Materials And Resins |
Sales | $50,000,000-$100,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 348,480 |
Annual Production | 100,000,000 Units |
Production Hrs. Annual | 8,760 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $468,045 | 10,783,720 | kWh | $0.04 |
Electricity Demand | $121,416 | 20,496 | kW-months/year | $5.92 |
Electricity Fees | $4,842 | - | $ | - |
Natural Gas | $185,362 | 71,395 | MMBtu | $2.60 |
TOTAL ENERGY COSTS | $779,665 | |||
RECOMMENDED SAVINGS* | $45,490 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $21,406 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Primary Raw Material | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Primary Raw Material | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $12,552 Cost: $1,970 |
- | - | - | - | $3,630 | 1,323 | $4,629 | 1,273 | - | - | - | - | $4,293 | - |
- - kWh |
- - kW-months/year |
$3,630 1,323 MMBtu |
$4,629 1,273 Tgal |
- - $ |
- - $ |
$4,293 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD |
Savings: $15,952 Cost: $28,542 |
$2,347 | 44,834 | $405 | 61 | - | - | - | - | $13,200 | - | - | - | - | - |
$2,347 44,834 kWh |
$405 61 kW-months/year |
- - MMBtu |
- - Tgal |
$13,200 - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $6,311 Cost: $2,097 |
- | - | - | - | $6,311 | 2,456 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$6,311 2,456 MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.131 MODIFY PROCESS TO REDUCE MATERIAL USE/COST |
Savings: $8,000 Cost: $24,775 |
- | - | - | - | - | - | - | - | - | - | $8,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
$8,000 - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.5123 REDUCE FLUID FLOW RATES |
Savings: $1,821 Cost: $3,221 |
$1,821 | 42,050 | - | - | - | - | - | - | - | - | - | - | - | - |
$1,821 42,050 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $854 Cost: - |
$407 | 9,399 | $447 | 68 | - | - | - | - | - | - | - | - | - | - |
$407 9,399 kWh |
$447 68 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $45,490 Cost: $60,605 |
$4,575 | 96,283 | $852 | 129 | $9,941 | 3,779 | $4,629 | 1,273 | $13,200 | - | $8,000 | - | $4,293 | - | $4,575 96,283 kWh |
$852 129 kW-months/year |
$9,941 3,779 MMBtu |
$4,629 1,273 Tgal |
$13,200 - $ |
$8,000 - $ |
$4,293 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $21,406 Cost: $26,745 |
$407 | 9,399 | $447 | 68 | $3,630 | 1,323 | $4,629 | 1,273 | - | - | $8,000 | - | $4,293 | - | $407 9,399 kWh |
$447 68 kW-months/year |
$3,630 1,323 MMBtu |
$4,629 1,273 Tgal |
- - $ |
$8,000 - $ |
$4,293 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Primary Raw Material | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Primary Raw Material | Water Consumption |