IAC Assessment: OR0720
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0720
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2019
Principal Product Packed Apples
NAICS 111331 - Apple Orchards
SIC 0175 - Deciduous Tree Fruits
Sales $10,000,000-$50,000,000
# of Employees 115
Plant Area (Sq.Ft.) 183,000
Annual Production 1,000,000 Units
Production Hrs. Annual 8,760
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $185,461 10,860,340 kWh $0.02
TOTAL ENERGY COSTS $185,461
RECOMMENDED SAVINGS* $68,101 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $35,763
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ $ $ $
01: 3.3128 UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS Savings:
$27,061
Cost:
$33,855
$(-1,615) (-65,323) - - - - $29,000 - $(-324) - $(-1,615)
(-65,323)
kWh
-
-
kW-months/year
-
-
$
$29,000
-
$
$(-324)
-
$
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$31,433
Cost:
$68,000
- - - - $31,433 - - - - - -
-
kWh
-
-
kW-months/year
$31,433
-
$
-
-
$
-
-
$
03: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$4,330
Cost:
$1,100
$3,947 159,649 $383 219 - - - - - - $3,947
159,649
kWh
$383
219
kW-months/year
-
-
$
-
-
$
-
-
$
04: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT Savings:
$3,139
Cost:
$2,013
$2,539 102,796 $600 343 - - - - - - $2,539
102,796
kWh
$600
343
kW-months/year
-
-
$
-
-
$
-
-
$
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,138
Cost:
$3,275
$1,949 78,849 $189 108 - - - - - - $1,949
78,849
kWh
$189
108
kW-months/year
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$68,101
Cost:
$108,243
$6,820 275,971 $1,172 670 $31,433 - $29,000 - $(-324) - $6,820
275,971
kWh
$1,172
670
kW-months/year
$31,433
-
$
$29,000
-
$
$(-324)
-
$
TOTAL IMPLEMENTED Savings:
$35,763
Cost:
$69,100
$3,947 159,649 $383 219 $31,433 - - - - - $3,947
159,649
kWh
$383
219
kW-months/year
$31,433
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost