Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2022 |
Principal Product | Aggregate Industry Equipment |
NAICS | 333120 - Construction Machinery Manufacturing |
SIC | 3531 - Construction Machinery |
Sales | $50,000,000-$100,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 180,000 |
Annual Production | 310 Units |
Production Hrs. Annual | 5,916 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $189,522 | 2,614,097 | kWh | $0.07 |
Electricity Demand | $41,954 | 7,221 | kW-months/year | $5.81 |
Electricity Fees | $5,225 | - | $ | - |
Natural Gas | $28,109 | 4,432 | MMBtu | $6.34 |
LPG | $47,231 | 1,471 | MMBtu | $32.11 |
TOTAL ENERGY COSTS | $312,041 | |||
RECOMMENDED SAVINGS* | $146,969 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $146,969 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | LPG | Other Liquid (non-haz) | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | LPG | Other Liquid (non-haz) | Administrative Changes | Ancillary Material Cost | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $6,763 Cost: $1,880 |
$2,576 | 35,531 | $4,187 | 721 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$2,576 35,531 kWh |
$4,187 721 kW-months/year |
- - $ |
- - MMBtu |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.5111 FILTER AND REUSE HYDRAULIC OIL |
Savings: $34,830 Cost: $88,699 |
- | - | - | - | - | - | - | - | - | - | $31,784 | 972 | - | - | $3,000 | - | $46 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - MMBtu |
$31,784 972 gal |
- - $ |
$3,000 - $ |
$46 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $3,913 Cost: $10,533 |
- | - | - | - | $3,913 | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,913 - $ |
- - MMBtu |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8227 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION |
Savings: $99,431 Cost: $292,453 |
$(-7,204) | (-99,372) | - | - | - | - | - | - | $47,231 | 1,471 | - | - | $59,404 | - | - | - | - | - |
$(-7,204) (-99,372) kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$47,231 1,471 MMBtu |
- - gal |
$59,404 - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,032 Cost: $9,520 |
- | - | - | - | - | - | $2,032 | 358 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$2,032 358 MMBtu |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $146,969 Cost: $403,085 |
$(-4,628) | (-63,841) | $4,187 | 721 | $3,913 | - | $2,032 | 358 | $47,231 | 1,471 | $31,784 | 972 | $59,404 | - | $3,000 | - | $46 | - | $(-4,628) (-63,841) kWh |
$4,187 721 kW-months/year |
$3,913 - $ |
$2,032 358 MMBtu |
$47,231 1,471 MMBtu |
$31,784 972 gal |
$59,404 - $ |
$3,000 - $ |
$46 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $146,969 Cost: $403,085 |
$(-4,628) | (-63,841) | $4,187 | 721 | $3,913 | - | $2,032 | 358 | $47,231 | 1,471 | $31,784 | 972 | $59,404 | - | $3,000 | - | $46 | - | $(-4,628) (-63,841) kWh |
$4,187 721 kW-months/year |
$3,913 - $ |
$2,032 358 MMBtu |
$47,231 1,471 MMBtu |
$31,784 972 gal |
$59,404 - $ |
$3,000 - $ |
$46 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | LPG | Other Liquid (non-haz) | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | LPG | Other Liquid (non-haz) | Administrative Changes | Ancillary Material Cost | Water Consumption |