Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2022 |
Principal Product | Fruit/vegetable puree |
NAICS | 311411 - Frozen Fruit, Juice, and Vegetable Manufacturing |
SIC | 2037 - Frozen Fruits And Vegetables |
Sales | $50,000,000-$100,000,000 |
# of Employees | 750 |
Plant Area (Sq.Ft.) | 325,000 |
Annual Production | 112,000,000 Pounds |
Production Hrs. Annual | 7,200 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $326,718 | 7,393,127 | kWh | $0.04 |
Electricity Demand | $252,339 | 26,919 | kW-months/year | $9.37 |
Electricity Fees | $46,664 | - | $ | - |
Natural Gas | $67,439 | 70,440 | MMBtu | $0.96 |
TOTAL ENERGY COSTS | $693,160 | |||
RECOMMENDED SAVINGS* | $320,112 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,612 Cost: - |
$1,147 | 26,856 | $465 | 45 | - | - | - | - |
$1,147 26,856 kWh |
$465 45 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES |
Savings: $26,900 Cost: - |
- | - | - | - | - | - | $26,900 | - |
- - kWh |
- - kW-months/year |
- - $ |
$26,900 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $97,200 Cost: $50,000 |
- | - | - | - | $97,200 | - | - | - |
- - kWh |
- - kW-months/year |
$97,200 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $194,400 Cost: $300,000 |
- | - | - | - | $194,400 | - | - | - |
- - kWh |
- - kW-months/year |
$194,400 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $320,112 Cost: $350,000 |
$1,147 | 26,856 | $465 | 45 | $291,600 | - | $26,900 | - | $1,147 26,856 kWh |
$465 45 kW-months/year |
$291,600 - $ |
$26,900 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost |