Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 1999 |
Principal Product | Plumbing fixtures |
NAICS | n/a |
SIC | 3432 - Plumbing Fixture Fittings And Trim |
Sales | $10,000,000-$50,000,000 |
# of Employees | 145 |
Plant Area (Sq.Ft.) | 133,000 |
Annual Production | 8,000,000 Pieces |
Production Hrs. Annual | 4,000 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $133,211 | 2,678,781 | kWh | $0.05 |
Electricity Demand | $79,791 | 8,377 | kW-months/year | $9.53 |
Electricity Fees | $3,588 | - | $ | - |
Natural Gas | $18,202 | 3,538 | MMBtu | $5.14 |
TOTAL ENERGY COSTS | $239,985 | |||
RECOMMENDED SAVINGS* | $80,115 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,115 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $331 Cost: $725 |
$291 | 5,862 | $40 | 4 | - | - | - | - | - | - |
$291 5,862 kWh |
$40 4 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,292 Cost: $360 |
$2,840 | 57,151 | $1,452 | 152 | - | - | - | - | - | - |
$2,840 57,151 kWh |
$1,452 152 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $940 Cost: $584 |
$940 | 19,050 | - | - | - | - | - | - | - | - |
$940 19,050 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,392 Cost: $1,394 |
- | - | - | - | $1,392 | 279 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,392 279 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.7311 MAINTAIN MACHINES TO REDUCE LEAKS |
Savings: $6,160 Cost: - |
- | - | - | - | - | - | $6,160 | 24,000 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$6,160 24,000 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.446 AUTOMATE FINISHING PROCESS |
Savings: $67,000 Cost: $9,000 |
- | - | - | - | - | - | - | - | $67,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$67,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $80,115 Cost: $12,063 |
$4,071 | 82,063 | $1,492 | 156 | $1,392 | 279 | $6,160 | 24,000 | $67,000 | - | $4,071 82,063 kWh |
$1,492 156 kW-months/year |
$1,392 279 MMBtu |
$6,160 24,000 lb |
$67,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,115 Cost: $3,063 |
$4,071 | 82,063 | $1,492 | 156 | $1,392 | 279 | $6,160 | 24,000 | - | - | $4,071 82,063 kWh |
$1,492 156 kW-months/year |
$1,392 279 MMBtu |
$6,160 24,000 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Primary Product |