Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2002 |
Principal Product | beer |
NAICS | n/a |
SIC | 2085 - Distilled And Blended Liquors |
Sales | $10,000,000-$50,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 20,000 |
Annual Production | 20,000 BBL |
Production Hrs. Annual | 3,500 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $44,167 | 310,080 | kWh | $0.14 |
Electricity Demand | $12,301 | 1,085 | kW-months/year | $11.34 |
Electricity Fees | $537 | - | $ | - |
Natural Gas | $42,120 | 3,519 | MMBtu | $11.97 |
TOTAL ENERGY COSTS | $119,735 | |||
RECOMMENDED SAVINGS* | $29,009 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,904 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Disposal | Electricity Usage | Natural Gas | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT |
Savings: $9,512 Cost: $6,000 |
- | - | $9,512 | 793 | - | - |
- - kWh |
$9,512 793 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2522 ISOLATE HOT OR COLD EQUIPMENT |
Savings: $3,123 Cost: $5,200 |
$3,123 | 21,945 | - | - | - | - |
$3,123 21,945 kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1221 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES |
Savings: $4,969 Cost: $2,000 |
- | - | $4,969 | 414 | - | - |
- - kWh |
$4,969 414 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2694 USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE |
Savings: $501 Cost: $20 |
$501 | 12 | - | - | - | - |
$501 12 kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $10,904 Cost: $2,000 |
- | - | - | - | $10,904 | - |
- - kWh |
- - MMBtu |
$10,904 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $29,009 Cost: $15,220 |
$3,624 | 21,957 | $14,481 | 1,207 | $10,904 | - | $3,624 21,957 kWh |
$14,481 1,207 MMBtu |
$10,904 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,904 Cost: $2,000 |
- | - | - | - | $10,904 | - | - - kWh |
- - MMBtu |
$10,904 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Disposal | Electricity Usage | Natural Gas | Water Disposal |