IAC Assessment: SD0307
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0307
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 2002
Principal Product Cheese
NAICS n/a
SIC 2022 - Cheese, Natural And Processed
Sales $10,000,000-$50,000,000
# of Employees 14
Plant Area (Sq.Ft.) 22,000
Annual Production 4,000,000 Pounds
Production Hrs. Annual 5,460
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $106,071 1,265,250 kWh $0.08
Electricity Demand $9,137 3,326 kW-months/year $2.75
Electricity Fees $3,439 - $ -
Natural Gas $51,911 11,565 MMBtu $4.49
TOTAL ENERGY COSTS $170,558
RECOMMENDED SAVINGS* $126,506 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)
$ kWh $ kW-months/year $ MMBtu $ lb
01: 2.3417 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT Savings:
$115,174
Cost:
$476,400
$106,028 2,031,120 $9,146 3,326 - - - - $106,028
2,031,120
kWh
$9,146
3,326
kW-months/year
-
-
MMBtu
-
-
lb
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$6,963
Cost:
$18,000
- - - - $6,963 1,645 - - -
-
kWh
-
-
kW-months/year
$6,963
1,645
MMBtu
-
-
lb
03: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,517
Cost:
$2,500
$1,517 3,600 - - - - - - $1,517
3,600
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$933
Cost:
$1,200
$933 11,138 - - - - - - $933
11,138
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
05: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$785
Cost:
-
$732 8,736 $53 19 - - - - $732
8,736
kWh
$53
19
kW-months/year
-
-
MMBtu
-
-
lb
06: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$1,134
Cost:
$5,000
- - - - - - $1,134 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,134
-
lb
TOTAL RECOMMENDED Savings:
$126,506
Cost:
$503,100
$109,210 2,054,594 $9,199 3,345 $6,963 1,645 $1,134 - $109,210
2,054,594
kWh
$9,199
3,345
kW-months/year
$6,963
1,645
MMBtu
$1,134
-
lb
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)