Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2005 |
Principal Product | corrugated boxes and containers |
NAICS | 322211 - Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 70 |
Plant Area (Sq.Ft.) | 125,000 |
Annual Production | 30,000,000 Pieces |
Production Hrs. Annual | 4,335 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $176,184 | 1,996,579 | kWh | $0.09 |
Electricity Demand | $85,757 | 8,236 | kW-months/year | $10.41 |
TOTAL ENERGY COSTS | $261,941 | |||
RECOMMENDED SAVINGS* | $46,467 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $12,734 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $5,391 Cost: $11,000 |
$5,391 | 61,121 | - | - | - | - | - | - | - | - |
$5,391 61,121 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,992 Cost: $14,000 |
$4,992 | 56,593 | - | - | - | - | - | - | - | - |
$4,992 56,593 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,583 Cost: $7,647 |
$2,698 | 30,656 | $885 | 85 | - | - | - | - | - | - |
$2,698 30,656 kWh |
$885 85 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,351 Cost: $120 |
$1,771 | 20,082 | $580 | 56 | - | - | - | - | - | - |
$1,771 20,082 kWh |
$580 56 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,151 Cost: - |
$1,151 | 13,046 | - | - | - | - | - | - | - | - |
$1,151 13,046 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $18,769 Cost: $25,650 |
$2,138 | 24,245 | $700 | 67 | $(-8,069) | (-1,008) | $24,000 | - | - | - |
$2,138 24,245 kWh |
$700 67 kW-months/year |
$(-8,069) (-1,008) MMBtu |
$24,000 - gal |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $10,230 Cost: $18,500 |
- | - | - | - | - | - | - | - | $10,230 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$10,230 - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $46,467 Cost: $76,917 |
$18,141 | 205,743 | $2,165 | 208 | $(-8,069) | (-1,008) | $24,000 | - | $10,230 | - | $18,141 205,743 kWh |
$2,165 208 kW-months/year |
$(-8,069) (-1,008) MMBtu |
$24,000 - gal |
$10,230 - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $12,734 Cost: $25,120 |
$12,154 | 137,796 | $580 | 56 | - | - | - | - | - | - | $12,154 137,796 kWh |
$580 56 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||