IAC Assessment: SD0356
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0356
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 2005
Principal Product corrugated boxes and containers
NAICS 322211 - Corrugated and Solid Fiber Box Manufacturing
SIC 2653 - Corrugated And Solid Fiber Boxes
Sales $10,000,000-$50,000,000
# of Employees 70
Plant Area (Sq.Ft.) 125,000
Annual Production 30,000,000 Pieces
Production Hrs. Annual 4,335
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $176,184 1,996,579 kWh $0.09
Electricity Demand $85,757 8,236 kW-months/year $10.41
TOTAL ENERGY COSTS $261,941
RECOMMENDED SAVINGS* $46,467 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $12,734
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz)
$ kWh $ kW-months/year $ MMBtu $ gal $ lb
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$5,391
Cost:
$11,000
$5,391 61,121 - - - - - - - - $5,391
61,121
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4,992
Cost:
$14,000
$4,992 56,593 - - - - - - - - $4,992
56,593
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$3,583
Cost:
$7,647
$2,698 30,656 $885 85 - - - - - - $2,698
30,656
kWh
$885
85
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,351
Cost:
$120
$1,771 20,082 $580 56 - - - - - - $1,771
20,082
kWh
$580
56
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,151
Cost:
-
$1,151 13,046 - - - - - - - - $1,151
13,046
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
06: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL Savings:
$18,769
Cost:
$25,650
$2,138 24,245 $700 67 $(-8,069) (-1,008) $24,000 - - - $2,138
24,245
kWh
$700
67
kW-months/year
$(-8,069)
(-1,008)
MMBtu
$24,000
-
gal
-
-
lb
07: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$10,230
Cost:
$18,500
- - - - - - - - $10,230 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$10,230
-
lb
TOTAL RECOMMENDED Savings:
$46,467
Cost:
$76,917
$18,141 205,743 $2,165 208 $(-8,069) (-1,008) $24,000 - $10,230 - $18,141
205,743
kWh
$2,165
208
kW-months/year
$(-8,069)
(-1,008)
MMBtu
$24,000
-
gal
$10,230
-
lb
TOTAL IMPLEMENTED Savings:
$12,734
Cost:
$25,120
$12,154 137,796 $580 56 - - - - - - $12,154
137,796
kWh
$580
56
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ lb
Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz)