Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2014 |
Principal Product | Wine |
NAICS | 312130 - Wineries |
SIC | 2084 - Wines, Brandy, And Brandy Spirits |
Sales | $10,000,000-$50,000,000 |
# of Employees | 35 |
Plant Area (Sq.Ft.) | 305,000 |
Annual Production | 4,800,000 Pieces |
Production Hrs. Annual | 3,783 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $139,376 | 1,514,918 | kWh | $0.09 |
Electricity Demand | $110,453 | 4,947 | kW-months/year | $22.33 |
Electricity Fees | $7,960 | - | $ | - |
Natural Gas | $31,803 | 3,947 | MMBtu | $8.06 |
TOTAL ENERGY COSTS | $289,592 | |||
RECOMMENDED SAVINGS* | $77,624 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $12,013 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $6,757 Cost: - |
$735 | 7,241 | - | - | $6,022 | 747 | - | - |
$735 7,241 kWh |
- - kW-months/year |
$6,022 747 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,693 Cost: $650 |
$2,693 | 26,517 | - | - | - | - | - | - |
$2,693 26,517 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $29,874 Cost: $19,111 |
$29,874 | 294,176 | - | - | - | - | - | - |
$29,874 294,176 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $30,675 Cost: $77,383 |
$8,885 | 87,493 | $7,340 | 329 | - | - | $14,450 | - |
$8,885 87,493 kWh |
$7,340 329 kW-months/year |
- - MMBtu |
$14,450 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $5,062 Cost: $12,000 |
$4,085 | 40,224 | $977 | 44 | - | - | - | - |
$4,085 40,224 kWh |
$977 44 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,563 Cost: $11,811 |
$1,516 | 14,929 | $1,047 | 47 | - | - | - | - |
$1,516 14,929 kWh |
$1,047 47 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $77,624 Cost: $120,955 |
$47,788 | 470,580 | $9,364 | 419 | $6,022 | 747 | $14,450 | - | $47,788 470,580 kWh |
$9,364 419 kW-months/year |
$6,022 747 MMBtu |
$14,450 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $12,013 Cost: $12,461 |
$4,944 | 48,687 | $1,047 | 47 | $6,022 | 747 | - | - | $4,944 48,687 kWh |
$1,047 47 kW-months/year |
$6,022 747 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |