Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2020 |
Principal Product | In-Shell Walnuts, raw walnuts, walnut oil |
NAICS | 311911 - Roasted Nuts and Peanut Butter Manufacturing |
SIC | 2068 - Salted And Roasted Nuts And Seeds |
Sales | $10,000,000-$50,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 40,000 |
Annual Production | 3,000,000 Pounds |
Production Hrs. Annual | 5,136 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $100,530 | 811,604 | kWh | $0.12 |
Electricity Demand | $71,534 | 4,308 | kW-months/year | $16.60 |
LPG | $32,926 | 1,715 | MMBtu | $19.20 |
TOTAL ENERGY COSTS | $204,990 | |||
RECOMMENDED SAVINGS* | $121,645 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $121,645 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Primary Product | Electricity Usage | Electricity Demand | Personnel Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,333 Cost: - |
$4,413 | 35,627 | - | - | $(-1,080) | - | - | - |
$4,413 35,627 kWh |
- - kW-months/year |
$(-1,080) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,905 Cost: $120 |
$2,447 | 19,757 | $458 | 28 | - | - | - | - |
$2,447 19,757 kWh |
$458 28 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $289 Cost: $41 |
$289 | 2,329 | - | - | - | - | - | - |
$289 2,329 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $2,096 Cost: $2,344 |
$2,096 | 16,918 | - | - | - | - | - | - |
$2,096 16,918 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $12,409 Cost: $22,495 |
$8,971 | 72,426 | $2,590 | 156 | $674 | - | $174 | - |
$8,971 72,426 kWh |
$2,590 156 kW-months/year |
$674 - $ |
$174 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $100,613 Cost: $451,750 |
$70,737 | 571,057 | $29,876 | 1,799 | - | - | - | - |
$70,737 571,057 kWh |
$29,876 1,799 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $121,645 Cost: $476,750 |
$88,953 | 718,114 | $32,924 | 1,983 | $(-406) | - | $174 | - | $88,953 718,114 kWh |
$32,924 1,983 kW-months/year |
$(-406) - $ |
$174 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $121,645 Cost: $476,750 |
$88,953 | 718,114 | $32,924 | 1,983 | $(-406) | - | $174 | - | $88,953 718,114 kWh |
$32,924 1,983 kW-months/year |
$(-406) - $ |
$174 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Primary Product | Electricity Usage | Electricity Demand | Personnel Changes | Primary Product |