IAC Assessment: SF0607
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0607
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2023
Principal Product Cans for fruit and vegetables
NAICS 332431 - Metal Can Manufacturing
SIC 3411 - Metal Cans
Sales $50,000,000-$100,000,000
# of Employees 200
Plant Area (Sq.Ft.) 152,000
Annual Production 580,000,000 Units
Production Hrs. Annual 6,000
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $508,561 6,369,278 kWh $0.08
Electricity Demand $271,274 15,048 kW-months/year $18.03
Electricity Fees $3,716 - $ -
Natural Gas $368,672 35,690 MMBtu $10.33
TOTAL ENERGY COSTS $1,152,223
RECOMMENDED SAVINGS* $82,479 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$6,168
Cost:
-
$6,168 77,295 - - $6,168
77,295
kWh
-
-
MMBtu
02: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$3,963
Cost:
$344
$535 6,706 $3,428 332 $535
6,706
kWh
$3,428
332
MMBtu
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$16,399
Cost:
$8,086
$16,399 205,501 - - $16,399
205,501
kWh
-
-
MMBtu
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$8,524
Cost:
$11,610
$8,524 106,814 - - $8,524
106,814
kWh
-
-
MMBtu
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4,254
Cost:
$13,352
$4,254 53,315 - - $4,254
53,315
kWh
-
-
MMBtu
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,111
Cost:
$9,578
$2,111 26,449 - - $2,111
26,449
kWh
-
-
MMBtu
07: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$41,060
Cost:
$346,427
$41,060 514,540 - - $41,060
514,540
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$82,479
Cost:
$389,397
$79,051 990,620 $3,428 332 $79,051
990,620
kWh
$3,428
332
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas