Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Syracuse University |
---|---|
Assessment Year | 2001 |
Principal Product | packaging machinery |
NAICS | n/a |
SIC | 3559 - Special Industry Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 77,500 |
Annual Production | 100 Pieces |
Production Hrs. Annual | 4,940 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $39,307 | 722,240 | kWh | $0.05 |
Electricity Demand | $28,694 | 2,376 | kW-months/year | $12.08 |
Electricity Fees | $9,657 | - | $ | - |
Natural Gas | $24,368 | 1,695 | MMBtu | $14.38 |
TOTAL ENERGY COSTS | $102,026 | |||
RECOMMENDED SAVINGS* | $22,116 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,599 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.452 ELIMINATE SHIFT |
Savings: $13,517 Cost: - |
$11,403 | 207,740 | - | - | $2,114 | 93 | - | - | - | - |
$11,403 207,740 kWh |
- - kW-months/year |
$2,114 93 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,968 Cost: $694 |
- | - | - | - | $2,968 | 238 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,968 238 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $2,325 Cost: $7,060 |
$1,287 | 32,169 | $1,038 | 78 | - | - | - | - | - | - |
$1,287 32,169 kWh |
$1,038 78 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8118 CHECK FOR ACCURACY OF UTILITY / POWER METERS |
Savings: $1,800 Cost: - |
- | - | - | - | - | - | $1,200 | - | $600 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,200 - $ |
$600 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $739 Cost: - |
- | - | - | - | $739 | 12,096 | - | - | - | - |
- - kWh |
- - kW-months/year |
$739 12,096 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $378 Cost: $196 |
$378 | 7,191 | - | - | - | - | - | - | - | - |
$378 7,191 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $347 Cost: $117 |
$347 | 8,678 | - | - | - | - | - | - | - | - |
$347 8,678 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $42 Cost: $3 |
- | - | - | - | $42 | 5 | - | - | - | - |
- - kWh |
- - kW-months/year |
$42 5 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,116 Cost: $8,070 |
$13,415 | 255,778 | $1,038 | 78 | $5,863 | 12,432 | $1,200 | - | $600 | - | $13,415 255,778 kWh |
$1,038 78 kW-months/year |
$5,863 12,432 MMBtu |
$1,200 - $ |
$600 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,599 Cost: $8,070 |
$2,012 | 48,038 | $1,038 | 78 | $3,749 | 12,339 | $1,200 | - | $600 | - | $2,012 48,038 kWh |
$1,038 78 kW-months/year |
$3,749 12,339 MMBtu |
$1,200 - $ |
$600 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost |