IAC Assessment: SU0137
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SU0137
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Syracuse University
Assessment Year 2002
Principal Product #9 and #10 envelopes
NAICS n/a
SIC 2677 - Envelopes
Sales $10,000,000-$50,000,000
# of Employees 95
Plant Area (Sq.Ft.) 88,000
Annual Production 1,040,000,000 Units
Production Hrs. Annual 6,240
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $175,934 2,714,100 kWh $0.06
Electricity Demand $61,416 6,252 kW-months/year $9.82
Natural Gas $15,424 1,342 MMBtu $11.49
TOTAL ENERGY COSTS $252,774
RECOMMENDED SAVINGS* $23,840 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $18,799
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas
$ kWh $ kW-months/year $ $ $ MMBtu
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$111
Cost:
-
$111 1,810 - - - - - - $111
1,810
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
02: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$429
Cost:
$71
$414 6,895 $15 1 - - - - $414
6,895
kWh
$15
1
kW-months/year
-
-
$
-
-
MMBtu
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$806
Cost:
$2,150
$806 13,418 - - - - - - $806
13,418
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
04: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$923
Cost:
$3,750
- - - - $923 - - - -
-
kWh
-
-
kW-months/year
$923
-
$
-
-
MMBtu
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,228
Cost:
$327
$1,228 20,465 - - - - - - $1,228
20,465
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
06: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR Savings:
$3,312
Cost:
$327
- - - - - - $3,312 288 -
-
kWh
-
-
kW-months/year
-
-
$
$3,312
288
MMBtu
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$4,451
Cost:
-
$4,451 74,180 - - - - - - $4,451
74,180
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
08: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$12,580
Cost:
$510
$12,580 262,080 - - - - - - $12,580
262,080
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$23,840
Cost:
$7,135
$19,590 378,848 $15 1 $923 - $3,312 288 $19,590
378,848
kWh
$15
1
kW-months/year
$923
-
$
$3,312
288
MMBtu
TOTAL IMPLEMENTED Savings:
$18,799
Cost:
$908
$18,784 365,430 $15 1 - - - - $18,784
365,430
kWh
$15
1
kW-months/year
-
-
$
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas