Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
IAC Center | Syracuse University |
---|---|
Assessment Year | 2002 |
Principal Product | frozen foods |
NAICS | n/a |
SIC | 2099 - Food Preparations, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 266,000 |
Annual Production | 93,000,000 Pounds |
Production Hrs. Annual | 5,760 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $847,694 | 12,621,912 | kWh | $0.07 |
Electricity Demand | $151,200 | 29,731 | kW-months/year | $5.09 |
Natural Gas | $174,069 | 31,203 | MMBtu | $5.58 |
TOTAL ENERGY COSTS | $1,172,963 | |||
RECOMMENDED SAVINGS* | $69,650 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $280 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Other Energy | Water Disposal | Personnel Changes | Electricity Usage | Natural Gas | Other Energy | Water Disposal | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7211 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS |
Savings: $50,000 Cost: $250,000 |
- | - | - | - | - | - | - | - | $50,000 | - |
- - kWh |
- - MMBtu |
- - MMBtu |
- - Tgal |
$50,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $10,576 Cost: $10,750 |
- | - | - | - | - | - | $10,576 | 4,492,800 | - | - |
- - kWh |
- - MMBtu |
- - MMBtu |
$10,576 4,492,800 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $7,242 Cost: $23,410 |
- | - | - | - | $7,242 | 769 | - | - | - | - |
- - kWh |
- - MMBtu |
$7,242 769 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,309 Cost: $1,925 |
$1,309 | 27,267 | - | - | - | - | - | - | - | - |
$1,309 27,267 kWh |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $280 Cost: $25 |
$280 | 5,480 | - | - | - | - | - | - | - | - |
$280 5,480 kWh |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $193 Cost: $545 |
$193 | 4,015 | - | - | - | - | - | - | - | - |
$193 4,015 kWh |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $50 Cost: $129 |
- | - | $50 | 9 | - | - | - | - | - | - |
- - kWh |
$50 9 MMBtu |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $69,650 Cost: $286,784 |
$1,782 | 36,762 | $50 | 9 | $7,242 | 769 | $10,576 | 4,492,800 | $50,000 | - | $1,782 36,762 kWh |
$50 9 MMBtu |
$7,242 769 MMBtu |
$10,576 4,492,800 Tgal |
$50,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $280 Cost: $25 |
$280 | 5,480 | - | - | - | - | - | - | - | - | $280 5,480 kWh |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Other Energy | Water Disposal | Personnel Changes | Electricity Usage | Natural Gas | Other Energy | Water Disposal | Personnel Changes |