IAC Assessment: SU0260
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SU0260
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Syracuse University
Assessment Year 2007
Principal Product Plastic Injection Moldings
NAICS 326199 - All Other Plastics Product Manufacturing
SIC 3089 - Plastics Products, Nec
Sales $100,000,000-$500,000,000
# of Employees 490
Plant Area (Sq.Ft.) 264,000
Annual Production 2,147,483,647 Pieces
Production Hrs. Annual 8,760
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,610,796 23,151,044 kWh $0.07
Electricity Demand $8,398 38,868 kW-months/year $0.22
Electricity Fees $158,780 - $ -
Natural Gas $86,235 8,113 MMBtu $10.63
TOTAL ENERGY COSTS $1,864,209
RECOMMENDED SAVINGS* $200,044 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $39,234
#|Description Savings
Cost
Status Electricity Usage Electricity Demand One-time Revenue or Avoided Cost Electricity Usage Electricity Demand One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$24,228
Cost:
-
$24,123 344,618 $105 486 - - $24,123
344,618
kWh
$105
486
kW-months/year
-
-
$
02: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$4,676
Cost:
-
$4,676 66,800 - - - - $4,676
66,800
kWh
-
-
kW-months/year
-
-
$
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$4,312
Cost:
-
- - - - $4,312 - -
-
kWh
-
-
kW-months/year
$4,312
-
$
04: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$685
Cost:
-
$672 9,600 $13 60 - - $672
9,600
kWh
$13
60
kW-months/year
-
-
$
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$10,644
Cost:
$1,034
$10,595 150,934 $49 228 - - $10,595
150,934
kWh
$49
228
kW-months/year
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,677
Cost:
$490
$3,661 52,297 $16 72 - - $3,661
52,297
kWh
$16
72
kW-months/year
-
-
$
07: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES Savings:
$142
Cost:
$739
$142 2,026 - - - - $142
2,026
kWh
-
-
kW-months/year
-
-
$
08: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$151,680
Cost:
$914,460
- - - - $151,680 - -
-
kWh
-
-
kW-months/year
$151,680
-
$
TOTAL RECOMMENDED Savings:
$200,044
Cost:
$916,723
$43,869 626,275 $183 846 $155,992 - $43,869
626,275
kWh
$183
846
kW-months/year
$155,992
-
$
TOTAL IMPLEMENTED Savings:
$39,234
Cost:
$1,524
$39,051 557,449 $183 846 - - $39,051
557,449
kWh
$183
846
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand One-time Revenue or Avoided Cost Electricity Usage Electricity Demand One-time Revenue or Avoided Cost