IAC Assessment: SU0424
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SU0424
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Syracuse University
Assessment Year 2016
Principal Product Production machine and job shop
NAICS 333517 - Machine Tool Manufacturing
SIC 3599 - Industrial Machinery, Nec
Sales $5,000,000-$10,000,000
# of Employees 25
Plant Area (Sq.Ft.) 26,548
Annual Production 960,000 Pounds
Production Hrs. Annual 4,743
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $26,878 392,960 kWh $0.07
Electricity Demand $18,057 1,766 kW-months/year $10.22
Electricity Fees $5,437 - $ -
Natural Gas $1,664 181 MMBtu $9.19
TOTAL ENERGY COSTS $52,035
RECOMMENDED SAVINGS* $4,182 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,182
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$1,548
Cost:
-
- - - - - - - - $1,548 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$1,548
-
$
02: 2.7122 DISCONNECT BALLASTS Savings:
$145
Cost:
-
$86 1,224 $59 6 - - - - - - $86
1,224
kWh
$59
6
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
03: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$30
Cost:
-
- - - - - - - - $30 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$30
-
$
04: 3.1161 ELIMINATE/REDUCE AN OPERATION Savings:
$1,305
Cost:
$800
$(-43) (-608) $(-552) (-54) - - $802 - $1,098 - $(-43)
(-608)
kWh
$(-552)
(-54)
kW-months/year
-
-
MMBtu
$802
-
$
$1,098
-
$
05: 2.7314 REDUCE VENTILATION AIR Savings:
$346
Cost:
$512
$96 1,372 - - $250 29 - - - - $96
1,372
kWh
-
-
kW-months/year
$250
29
MMBtu
-
-
$
-
-
$
06: 2.4321 UPGRADE OBSOLETE EQUIPMENT Savings:
$42
Cost:
$114
$35 499 $7 1 - - - - - - $35
499
kWh
$7
1
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$293
Cost:
$778
$293 4,180 - - - - - - - - $293
4,180
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
08: 3.7312 IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS Savings:
$473
Cost:
$1,875
$473 6,753 - - - - - - - - $473
6,753
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$4,182
Cost:
$4,079
$940 13,420 $(-486) (-48) $250 29 $802 - $2,676 - $940
13,420
kWh
$(-486)
(-48)
kW-months/year
$250
29
MMBtu
$802
-
$
$2,676
-
$
TOTAL IMPLEMENTED Savings:
$4,182
Cost:
$4,079
$940 13,420 $(-486) (-48) $250 29 $802 - $2,676 - $940
13,420
kWh
$(-486)
(-48)
kW-months/year
$250
29
MMBtu
$802
-
$
$2,676
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost