Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1984 |
Principal Product | MOLDED PLASTIC PRODUCTS |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 190 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 780,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $249,912 | 5,402,110 | kWh | $0.05 |
Natural Gas | $19,603 | 3,835 | MMBtu | $5.11 |
TOTAL ENERGY COSTS | $269,515 | |||
RECOMMENDED SAVINGS* | $39,220 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $32,918 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $24,450 Cost: $5,000 |
$19,390 | 419,109 | $5,060 | 990 |
$19,390 419,109 kWh |
$5,060 990 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $1,593 Cost: $2,240 |
- | - | $1,593 | 312 |
- - kWh |
$1,593 312 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $2,315 Cost: $5,800 |
- | - | $2,315 | 454 |
- - kWh |
$2,315 454 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,424 Cost: $45 |
$5,424 | 117,233 | - | - |
$5,424 117,233 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $3,987 Cost: - |
$3,987 | 86,166 | - | - |
$3,987 86,166 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,451 Cost: $1,000 |
$1,451 | 31,360 | - | - |
$1,451 31,360 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $39,220 Cost: $14,085 |
$30,252 | 653,868 | $8,968 | 1,756 | $30,252 653,868 kWh |
$8,968 1,756 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $32,918 Cost: $8,285 |
$26,265 | 567,702 | $6,653 | 1,302 | $26,265 567,702 kWh |
$6,653 1,302 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||