IAC Assessment: TN0536
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: TN0536
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Tennessee
Assessment Year 1994
Principal Product Platform,dump,and dropframe truck trailers
NAICS n/a
SIC 3715 - Truck Trailers
Sales $50,000,000-$100,000,000
# of Employees 300
Plant Area (Sq.Ft.) 160,000
Annual Production 3,640 Pieces
Production Hrs. Annual 4,615
Location (State) TN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $266,403 3,652,696 kWh $0.07
Natural Gas $188,190 29,811 MMBtu $6.31
TOTAL ENERGY COSTS $454,593
RECOMMENDED SAVINGS* $504,582 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $501,058
#|Description Savings
Cost
Status Electricity Usage Natural Gas Water Disposal Other Liquid (non-haz) Other Liquid (haz) Electricity Usage Natural Gas Water Disposal Other Liquid (non-haz) Other Liquid (haz)
$ kWh $ MMBtu $ Tgal $ gal $ gal
01: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$25,358
Cost:
$11,960
- - $25,358 4,025 - - - - - - -
-
kWh
$25,358
4,025
MMBtu
-
-
Tgal
-
-
gal
-
-
gal
02: 2.7491 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS Savings:
$2,818
Cost:
$2,816
- - $2,818 447 - - - - - - -
-
kWh
$2,818
447
MMBtu
-
-
Tgal
-
-
gal
-
-
gal
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$2,717
Cost:
-
$2,717 37,222 - - - - - - - - $2,717
37,222
kWh
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
gal
04: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$2,311
Cost:
-
$2,311 31,653 - - - - - - - - $2,311
31,653
kWh
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
gal
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$2,161
Cost:
$2,055
$2,161 29,601 - - - - - - - - $2,161
29,601
kWh
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
gal
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,869
Cost:
$980
$1,869 25,498 - - - - - - - - $1,869
25,498
kWh
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
gal
07: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$706
Cost:
$1,835
$706 9,672 - - - - - - - - $706
9,672
kWh
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
gal
08: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$642
Cost:
-
$642 8,792 - - - - - - - - $642
8,792
kWh
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
gal
09: 3.2121 CONVERT TO ELECTROSTATIC POWDER COATING Savings:
$442,969
Cost:
$62,448
- - - - $442,969 9,983 - - - - -
-
kWh
-
-
MMBtu
$442,969
9,983
Tgal
-
-
gal
-
-
gal
10: 3.8143 RECYCLE CLEANING SOLVENT AND REUSE Savings:
$17,087
Cost:
$26,320
- - - - - - $17,087 15,370 - - -
-
kWh
-
-
MMBtu
-
-
Tgal
$17,087
15,370
gal
-
-
gal
11: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$5,944
Cost:
$8,480
- - - - - - - - $5,944 250,000 -
-
kWh
-
-
MMBtu
-
-
Tgal
-
-
gal
$5,944
250,000
gal
TOTAL RECOMMENDED Savings:
$504,582
Cost:
$116,894
$10,406 142,438 $28,176 4,472 $442,969 9,983 $17,087 15,370 $5,944 250,000 $10,406
142,438
kWh
$28,176
4,472
MMBtu
$442,969
9,983
Tgal
$17,087
15,370
gal
$5,944
250,000
gal
TOTAL IMPLEMENTED Savings:
$501,058
Cost:
$112,243
$9,700 132,766 $25,358 4,025 $442,969 9,983 $17,087 15,370 $5,944 250,000 $9,700
132,766
kWh
$25,358
4,025
MMBtu
$442,969
9,983
Tgal
$17,087
15,370
gal
$5,944
250,000
gal
Savings
Cost
$ kWh $ MMBtu $ Tgal $ gal $ gal
Electricity Usage Natural Gas Water Disposal Other Liquid (non-haz) Other Liquid (haz) Electricity Usage Natural Gas Water Disposal Other Liquid (non-haz) Other Liquid (haz)