Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1995 |
Principal Product | small electric motors |
NAICS | n/a |
SIC | 3316 - Cold Finishing Of Steel Shapes |
Sales | $50,000,000-$100,000,000 |
# of Employees | 474 |
Plant Area (Sq.Ft.) | 226,000 |
Annual Production | 12,000,000 Pieces |
Production Hrs. Annual | 4,165 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $983,163 | 22,361,372 | kWh | $0.04 |
Natural Gas | $122,028 | 38,036 | MMBtu | $3.21 |
TOTAL ENERGY COSTS | $2,568,849 | |||
RECOMMENDED SAVINGS* | $455,954 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $242,207 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Electricity Usage | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | gal | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $9,785 Cost: $5,640 |
$3,871 | 148,886 | $5,914 | 1,848 | - | - | - | - |
$3,871 148,886 kWh |
$5,914 1,848 MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $3,680 Cost: $12,800 |
- | - | $3,680 | 1,150 | - | - | - | - |
- - kWh |
$3,680 1,150 MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,531 Cost: $3,600 |
- | - | $2,531 | 791 | - | - | - | - |
- - kWh |
$2,531 791 MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $4,207 Cost: $990 |
$4,207 | 75,029 | - | - | - | - | - | - |
$4,207 75,029 kWh |
- - MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $17,212 Cost: $6,100 |
$20,175 | 211,606 | $(-2,963) | (-926) | - | - | - | - |
$20,175 211,606 kWh |
$(-2,963) (-926) MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $238,000 Cost: $2,250 |
- | - | - | - | - | - | $238,000 | - |
- - kWh |
- - MMBtu |
- - gal |
$238,000 - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5146 UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID |
Savings: $119,243 Cost: $20,200 |
- | - | - | - | $119,243 | 155,591 | - | - |
- - kWh |
- - MMBtu |
$119,243 155,591 gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $61,296 Cost: $75,000 |
- | - | - | - | $61,296 | 1,120,000 | - | - |
- - kWh |
- - MMBtu |
$61,296 1,120,000 gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $455,954 Cost: $126,580 |
$28,253 | 435,521 | $9,162 | 2,863 | $180,539 | 1,275,591 | $238,000 | - | $28,253 435,521 kWh |
$9,162 2,863 MMBtu |
$180,539 1,275,591 gal |
$238,000 - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $242,207 Cost: $3,240 |
$4,207 | 75,029 | - | - | - | - | $238,000 | - | $4,207 75,029 kWh |
- - MMBtu |
- - gal |
$238,000 - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | gal | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Electricity Usage | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) |