IAC logo
IAC Assessment: TN0612
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: TN0612
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Tennessee
Assessment Year 1997
Principal Product Custom thermoformed plastic parts
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 44
Plant Area (Sq.Ft.) 85,000
Annual Production 936,000 Pieces
Production Hrs. Annual 6,240
Location (State) TN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $87,556 2,684,056 kWh $0.03
Electricity Demand $70,824 8,159 kW-months/year $8.68
Electricity Fees $216 - $ -
Natural Gas $53,949 9,955 MMBtu $5.42
TOTAL ENERGY COSTS $218,016
RECOMMENDED SAVINGS* $73,234 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,604
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Primary Product Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Primary Product
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ $
01: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS Savings:
$65,520
Cost:
$36,000
- - - - - - - - - - $65,520 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
$65,520
-
$
02: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$2,210
Cost:
-
- - - - $2,210 410 - - - - - - -
-
kWh
-
-
kW-months/year
$2,210
410
MMBtu
-
-
Tgal
-
-
lb
-
-
$
03: 3.1291 ELIMINATE PRACTICE OF MIXING WASTE STREAMS Savings:
$2,004
Cost:
-
- - - - - - - - $2,004 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$2,004
-
lb
-
-
$
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,990
Cost:
-
$1,090 36,342 $900 96 - - - - - - - - $1,090
36,342
kWh
$900
96
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
05: 3.4155 METER WASTE WATER Savings:
$660
Cost:
$235
- - - - - - $660 - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$660
-
Tgal
-
-
lb
-
-
$
06: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$600
Cost:
$220
$380 12,603 $220 24 - - - - - - - - $380
12,603
kWh
$220
24
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
07: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT Savings:
$250
Cost:
$650
$250 8,206 - - - - - - - - - - $250
8,206
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
TOTAL RECOMMENDED Savings:
$73,234
Cost:
$37,105
$1,720 57,151 $1,120 120 $2,210 410 $660 - $2,004 - $65,520 - $1,720
57,151
kWh
$1,120
120
kW-months/year
$2,210
410
MMBtu
$660
-
Tgal
$2,004
-
lb
$65,520
-
$
TOTAL IMPLEMENTED Savings:
$2,604
Cost:
$220
$380 12,603 $220 24 - - - - $2,004 - - - $380
12,603
kWh
$220
24
kW-months/year
-
-
MMBtu
-
-
Tgal
$2,004
-
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Primary Product Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Primary Product