Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1997 |
Principal Product | 24 feet and 28 feet wide double section prefabricated homes |
NAICS | n/a |
SIC | 2451 - Mobile Homes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 147 |
Plant Area (Sq.Ft.) | 72,000 |
Annual Production | 1,200 Pieces |
Production Hrs. Annual | 2,250 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $26,730 | 505,276 | kWh | $0.05 |
Electricity Demand | $9,807 | 1,648 | kW-months/year | $5.95 |
Electricity Fees | $420 | - | $ | - |
Natural Gas | $24,409 | 3,331 | MMBtu | $7.33 |
TOTAL ENERGY COSTS | $129,966 | |||
RECOMMENDED SAVINGS* | $81,675 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,265 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.421 MODIFY CURRENT INCENTIVE PROGRAM |
Savings: $35,750 Cost: $10,000 |
- | - | - | - | - | - | - | - | $60,750 | - | $(-25,000) | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$60,750 - $ |
$(-25,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $24,190 Cost: $41,800 |
$(-560) | (-18,757) | - | - | - | - | $27,000 | - | $(-2,250) | - | - | - |
$(-560) (-18,757) kWh |
- - kW-months/year |
- - MMBtu |
$27,000 - lb |
$(-2,250) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $16,200 Cost: $9,300 |
- | - | - | - | $16,200 | 2,220 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$16,200 2,220 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $4,875 Cost: - |
- | - | - | - | - | - | $4,875 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$4,875 - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $340 Cost: $340 |
$115 | 3,810 | $225 | 24 | - | - | - | - | - | - | - | - |
$115 3,810 kWh |
$225 24 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $320 Cost: $580 |
$320 | 10,551 | - | - | - | - | - | - | - | - | - | - |
$320 10,551 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $81,675 Cost: $62,020 |
$(-125) | (-4,396) | $225 | 24 | $16,200 | 2,220 | $31,875 | - | $58,500 | - | $(-25,000) | - | $(-125) (-4,396) kWh |
$225 24 kW-months/year |
$16,200 2,220 MMBtu |
$31,875 - lb |
$58,500 - $ |
$(-25,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,265 Cost: $51,100 |
$(-560) | (-18,757) | - | - | $16,200 | 2,220 | $31,875 | - | $(-2,250) | - | - | - | $(-560) (-18,757) kWh |
- - kW-months/year |
$16,200 2,220 MMBtu |
$31,875 - lb |
$(-2,250) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes |