Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1998 |
Principal Product | Inner springs for bed mattresses and spring sets for sleeper |
NAICS | n/a |
SIC | 3429 - Hardware, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 1,000,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $91,397 | 2,106,682 | kWh | $0.04 |
Electricity Demand | $44,505 | 4,760 | kW-months/year | $9.35 |
Electricity Fees | $(-4) | - | $ | - |
LPG | $106,122 | 23,203 | MMBtu | $4.57 |
TOTAL ENERGY COSTS | $371,317 | |||
RECOMMENDED SAVINGS* | $86,834 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $86,364 |
#|Description |
Savings Cost |
Status | LPG | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Primary Product | LPG | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $74,290 Cost: $26,180 |
- | - | - | - | $(-40,000) | - | - | - | $114,290 | - |
- - MMBtu |
- - lb |
$(-40,000) - $ |
- - $ |
$114,290 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $5,440 Cost: $3,440 |
$5,440 | 1,190 | - | - | - | - | - | - | - | - |
$5,440 1,190 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $4,680 Cost: - |
- | - | $4,680 | - | - | - | - | - | - | - |
- - MMBtu |
$4,680 - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $1,200 Cost: - |
- | - | - | - | - | - | $1,200 | - | - | - |
- - MMBtu |
- - lb |
- - $ |
$1,200 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $754 Cost: $950 |
$754 | 165 | - | - | - | - | - | - | - | - |
$754 165 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $470 Cost: $1,125 |
$470 | 103 | - | - | - | - | - | - | - | - |
$470 103 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $86,834 Cost: $31,695 |
$6,664 | 1,458 | $4,680 | - | $(-40,000) | - | $1,200 | - | $114,290 | - | $6,664 1,458 MMBtu |
$4,680 - lb |
$(-40,000) - $ |
$1,200 - $ |
$114,290 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $86,364 Cost: $30,570 |
$6,194 | 1,355 | $4,680 | - | $(-40,000) | - | $1,200 | - | $114,290 | - | $6,194 1,355 MMBtu |
$4,680 - lb |
$(-40,000) - $ |
$1,200 - $ |
$114,290 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
LPG | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Primary Product | LPG | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Primary Product |