Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1998 |
Principal Product | Steel forgings and specialty tools |
NAICS | n/a |
SIC | 3462 - Iron And Steel Forgings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 76 |
Plant Area (Sq.Ft.) | 55,000 |
Annual Production | 12,000,000 Pounds |
Production Hrs. Annual | 5,355 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $263,417 | 8,283,705 | kWh | $0.03 |
Electricity Demand | $367,463 | 37,365 | kW-months/year | $9.83 |
Electricity Fees | $(-4,779) | - | $ | - |
Natural Gas | $58,884 | 9,663 | MMBtu | $6.09 |
TOTAL ENERGY COSTS | $692,800 | |||
RECOMMENDED SAVINGS* | $473,580 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,500 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.423 MOVE PRODUCT USING MECHANICAL MEANS |
Savings: $462,700 Cost: $440,300 |
- | - | - | - | - | - | - | - | - | - | $462,700 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$462,700 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,810 Cost: $5,000 |
$2,090 | 61,547 | $3,720 | 348 | - | - | - | - | - | - | - | - | - | - |
$2,090 61,547 kWh |
$3,720 348 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.3122 USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS |
Savings: $3,560 Cost: $2,500 |
- | - | - | - | - | - | $183 | 765 | - | - | - | - | $3,377 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$183 765 gal |
- - lb |
- - $ |
$3,377 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,130 Cost: $980 |
$100 | 2,931 | $1,030 | 96 | - | - | - | - | - | - | - | - | - | - |
$100 2,931 kWh |
$1,030 96 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $240 Cost: $550 |
- | - | - | - | $240 | 40 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$240 40 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.7131 USE A RAG RECYCLE SERVICE |
Savings: $140 Cost: - |
- | - | - | - | - | - | - | - | $780 | 1,600 | - | - | $(-640) | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$780 1,600 lb |
- - $ |
$(-640) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $473,580 Cost: $449,330 |
$2,190 | 64,478 | $4,750 | 444 | $240 | 40 | $183 | 765 | $780 | 1,600 | $462,700 | - | $2,737 | - | $2,190 64,478 kWh |
$4,750 444 kW-months/year |
$240 40 MMBtu |
$183 765 gal |
$780 1,600 lb |
$462,700 - $ |
$2,737 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,500 Cost: $8,480 |
$2,190 | 64,478 | $4,750 | 444 | - | - | $183 | 765 | - | - | - | - | $3,377 | - | $2,190 64,478 kWh |
$4,750 444 kW-months/year |
- - MMBtu |
$183 765 gal |
- - lb |
- - $ |
$3,377 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |