Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas Rio Grande Valley |
---|---|
Assessment Year | 2018 |
Principal Product | Breakers and Switches |
NAICS | 335313 - Switchgear and Switchboard Apparatus Manufacturing |
SIC | 3613 - Switchgear And Switchboard Apparatus |
Sales | $1,000,000-$5,000,000 |
# of Employees | 77 |
Plant Area (Sq.Ft.) | 64,614 |
Annual Production | 104,000,000 Pieces |
Production Hrs. Annual | 2,400 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $128,803 | 1,180,560 | kWh | $0.11 |
Electricity Demand | $3,042 | 517 | kW-months/year | $5.88 |
Natural Gas | $4,800 | 523 | MMBtu | $9.18 |
TOTAL ENERGY COSTS | $136,645 | |||
RECOMMENDED SAVINGS* | $32,484 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,910 |
#|Description |
Savings Cost |
Status | Electricity Fees | Electricity Fees | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $3,043 Cost: $12,500 |
$3,043 | - |
$3,043 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.5318 RECYCLE FLUORESCENT LAMPS |
Savings: $6,608 Cost: $13,260 |
$6,608 | - |
$6,608 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $814 Cost: - |
$814 | - |
$814 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7425 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD |
Savings: $2,987 Cost: $15,373 |
$2,987 | - |
$2,987 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2523 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS |
Savings: $17,718 Cost: $3,748 |
$17,718 | - |
$17,718 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $1,315 Cost: $14,000 |
$1,315 | - |
$1,315 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,484 Cost: $58,881 |
$32,484 | - | $32,484 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,910 Cost: $42,633 |
$10,910 | - | $10,910 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Fees | Electricity Fees |