IAC Assessment: TT0072
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: TT0072
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Tennessee Technological University
Assessment Year 2011
Principal Product Medium Voltage Switchgear
NAICS 335311 - Power, Distribution, and Specialty Transformer Manufacturing
SIC 3612 - Transformers, Except Electronic
Sales $100,000,000-$500,000,000
# of Employees 300
Plant Area (Sq.Ft.) 200,000
Annual Production 6,000 Pieces
Production Hrs. Annual 6,000
Location (State) TN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $196,354 5,041,186 kWh $0.04
Electricity Demand $205,883 13,235 kW-months/year $15.56
Natural Gas $133,487 17,571 MMBtu $7.60
TOTAL ENERGY COSTS $535,724
RECOMMENDED SAVINGS* $16,018 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $16,018
#|Description Savings
Cost
Status Natural Gas Natural Gas
$ MMBtu
01: 2.2211 USE OPTIMUM TEMPERATURE Savings:
$16,018
Cost:
-
$16,018 2,094 $16,018
2,094
MMBtu
TOTAL RECOMMENDED Savings:
$16,018
Cost:
-
$16,018 2,094 $16,018
2,094
MMBtu
TOTAL IMPLEMENTED Savings:
$16,018
Cost:
-
$16,018 2,094 $16,018
2,094
MMBtu
Savings
Cost
$ MMBtu
Natural Gas Natural Gas