Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2011 |
Principal Product | Coated Fabrics |
NAICS | 313320 - Fabric Coating Mills |
SIC | 2221 - Broadwoven Fabric Mills, Manmade |
Sales | $100,000,000-$500,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 160,000 |
Annual Production | 19,000,000 Units |
Production Hrs. Annual | 8,568 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $529,949 | 7,295,280 | kWh | $0.07 |
Natural Gas | $649,526 | 58,985 | MMBtu | $11.01 |
TOTAL ENERGY COSTS | $1,179,475 | |||
RECOMMENDED SAVINGS* | $47,933 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,743 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER |
Savings: $8,585 Cost: $29,500 |
$8,585 | 71,540 |
$8,585 71,540 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2314 REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT |
Savings: $10,364 Cost: $5,531 |
$10,364 | 148,055 |
$10,364 148,055 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $7,023 Cost: $1,480 |
$7,023 | 100,327 |
$7,023 100,327 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,720 Cost: $800 |
$6,720 | 96,010 |
$6,720 96,010 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2692 USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER |
Savings: $15,241 Cost: $12,500 |
$15,241 | 217,734 |
$15,241 217,734 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $47,933 Cost: $49,811 |
$47,933 | 633,666 | $47,933 633,666 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,743 Cost: $2,280 |
$13,743 | 196,337 | $13,743 196,337 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Usage |