IAC logo
IAC Assessment: TT0127
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: TT0127
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Tennessee Technological University
Assessment Year 2014
Principal Product Carpet
NAICS 314110 - Carpet and Rug Mills
SIC 2273 - Carpets And Rugs
Sales $50,000,000-$100,000,000
# of Employees 270
Plant Area (Sq.Ft.) 275,000
Annual Production 20,508 Thousand Feet
Production Hrs. Annual 5,460
Location (State) TN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $379,767 5,905,200 kWh $0.06
Electricity Demand $184,026 15,218 kW-months/year $12.09
Electricity Fees $(-43,063) - $ -
Natural Gas $327,212 48,002 MMBtu $6.82
TOTAL ENERGY COSTS $847,942
RECOMMENDED SAVINGS* $113,365 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $990
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$34,016
Cost:
$68,097
- - - - $34,016 4,990 -
-
kWh
-
-
kW-months/year
$34,016
4,990
MMBtu
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$73,188
Cost:
$228,000
$47,648 744,499 $25,540 2,112 - - $47,648
744,499
kWh
$25,540
2,112
kW-months/year
-
-
MMBtu
03: 2.4225 INSTALL COMMON HEADER ON COMPRESSORS Savings:
$5,171
Cost:
$25
$5,171 80,800 - - - - $5,171
80,800
kWh
-
-
kW-months/year
-
-
MMBtu
04: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT Savings:
$600
Cost:
$25
$477 7,446 $123 10 - - $477
7,446
kWh
$123
10
kW-months/year
-
-
MMBtu
05: 2.7122 DISCONNECT BALLASTS Savings:
$390
Cost:
$130
$310 4,840 $80 7 - - $310
4,840
kWh
$80
7
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$113,365
Cost:
$296,277
$53,606 837,585 $25,743 2,129 $34,016 4,990 $53,606
837,585
kWh
$25,743
2,129
kW-months/year
$34,016
4,990
MMBtu
TOTAL IMPLEMENTED Savings:
$990
Cost:
$155
$787 12,286 $203 17 - - $787
12,286
kWh
$203
17
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas