Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2015 |
Principal Product | Fabricated Metal Products |
NAICS | 332322 - Sheet Metal Work Manufacturing |
SIC | 3444 - Sheet Metalwork |
Sales | $50,000,000-$100,000,000 |
# of Employees | 376 |
Plant Area (Sq.Ft.) | 250,000 |
Annual Production | 27,000,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $710,523 | 10,589,635 | kWh | $0.07 |
Electricity Demand | $296,340 | 22,481 | kW-months/year | $13.18 |
Natural Gas | $290,121 | 39,305 | MMBtu | $7.38 |
TOTAL ENERGY COSTS | $1,296,984 | |||
RECOMMENDED SAVINGS* | $57,713 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $19,615 Cost: $36,000 |
- | - | $19,615 | 1,488 | - | - |
- - kWh |
$19,615 1,488 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $13,344 Cost: $10,000 |
- | - | - | - | $13,344 | 1,808 |
- - kWh |
- - kW-months/year |
$13,344 1,808 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $11,515 Cost: $3,000 |
$8,272 | 123,456 | $3,243 | 246 | - | - |
$8,272 123,456 kWh |
$3,243 246 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $6,597 Cost: $63 |
$4,738 | 70,711 | $1,859 | 141 | - | - |
$4,738 70,711 kWh |
$1,859 141 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,475 Cost: $3,500 |
$4,330 | 64,620 | $145 | 11 | - | - |
$4,330 64,620 kWh |
$145 11 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7122 DISCONNECT BALLASTS |
Savings: $1,276 Cost: $120 |
$669 | 9,984 | $607 | 46 | - | - |
$669 9,984 kWh |
$607 46 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $891 Cost: $275 |
$891 | 13,303 | - | - | - | - |
$891 13,303 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $57,713 Cost: $52,958 |
$18,900 | 282,074 | $25,469 | 1,932 | $13,344 | 1,808 | $18,900 282,074 kWh |
$25,469 1,932 kW-months/year |
$13,344 1,808 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |