Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2021 |
Principal Product | Pork Products |
NAICS | 311611 - Animal (except Poultry) Slaughtering |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $5,000,000-$10,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 69,000 |
Annual Production | 200,000 Units |
Production Hrs. Annual | 2,080 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $320,892 | 5,309,116 | kWh | $0.06 |
Electricity Demand | $159,807 | 11,102 | kW-months/year | $14.39 |
Natural Gas | $32,235 | 5,041 | MMBtu | $6.39 |
TOTAL ENERGY COSTS | $591,715 | |||
RECOMMENDED SAVINGS* | $39,375 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,184 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Water Usage | Electricity Usage | Electricity Demand | Electricity Fees | Water Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $12,890 Cost: $3,640 |
$12,890 | 213,408 | - | - | - | - | - | - |
$12,890 213,408 kWh |
- - kW-months/year |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $10,005 Cost: $10,000 |
- | - | - | - | $10,005 | - | - | - |
- - kWh |
- - kW-months/year |
$10,005 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,928 Cost: $300 |
$6,928 | 114,704 | - | - | - | - | - | - |
$6,928 114,704 kWh |
- - kW-months/year |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4159 REPLACE TREATED WATER WITH WELL / SURFACE WATER |
Savings: $4,069 Cost: $16,500 |
- | - | - | - | - | - | $4,069 | 623 |
- - kWh |
- - kW-months/year |
- - $ |
$4,069 623 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,791 Cost: $1,660 |
$2,791 | 46,209 | - | - | - | - | - | - |
$2,791 46,209 kWh |
- - kW-months/year |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,508 Cost: $3,500 |
$471 | 7,800 | $1,037 | 72 | - | - | - | - |
$471 7,800 kWh |
$1,037 72 kW-months/year |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $783 Cost: $700 |
$783 | 12,965 | - | - | - | - | - | - |
$783 12,965 kWh |
- - kW-months/year |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $401 Cost: $553 |
$401 | 6,638 | - | - | - | - | - | - |
$401 6,638 kWh |
- - kW-months/year |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $39,375 Cost: $36,853 |
$24,264 | 401,724 | $1,037 | 72 | $10,005 | - | $4,069 | 623 | $24,264 401,724 kWh |
$1,037 72 kW-months/year |
$10,005 - $ |
$4,069 623 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,184 Cost: $1,253 |
$1,184 | 19,603 | - | - | - | - | - | - | $1,184 19,603 kWh |
- - kW-months/year |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Water Usage | Electricity Usage | Electricity Demand | Electricity Fees | Water Usage |