Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2022 |
Principal Product | Door hinges, Thresholds, Weatherstripping |
NAICS | 332321 - Metal Window and Door Manufacturing |
SIC | 3442 - Metal Doors, Sash, And Trim |
Sales | $50,000,000-$100,000,000 |
# of Employees | 158 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 3,500 Units |
Production Hrs. Annual | 2,860 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $76,040 | 1,012,800 | kWh | $0.08 |
Electricity Demand | $41,608 | 3,432 | kW-months/year | $12.12 |
Natural Gas | $7,421 | 994 | MMBtu | $7.47 |
TOTAL ENERGY COSTS | $126,690 | |||
RECOMMENDED SAVINGS* | $17,626 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,109 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $5,185 Cost: $9,150 |
$3,388 | 45,122 | $(-85) | (-7) | $1,882 | 252 | - | - |
$3,388 45,122 kWh |
$(-85) (-7) kW-months/year |
$1,882 252 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $4,579 Cost: $18,000 |
$3,655 | 48,662 | $267 | 22 | $657 | 88 | - | - |
$3,655 48,662 kWh |
$267 22 kW-months/year |
$657 88 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $2,258 Cost: $2,000 |
$299 | 3,983 | $61 | 5 | - | - | $1,898 | - |
$299 3,983 kWh |
$61 5 kW-months/year |
- - MMBtu |
$1,898 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,530 Cost: - |
$1,530 | 20,371 | - | - | - | - | - | - |
$1,530 20,371 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $1,507 Cost: $2,040 |
$(-1,616) | (-21,522) | $3,123 | 258 | - | - | - | - |
$(-1,616) (-21,522) kWh |
$3,123 258 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4237 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING |
Savings: $1,438 Cost: $1,240 |
$1,438 | 19,256 | - | - | - | - | - | - |
$1,438 19,256 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,129 Cost: $1,700 |
$1,129 | 15,030 | - | - | - | - | - | - |
$1,129 15,030 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $17,626 Cost: $34,130 |
$9,823 | 130,902 | $3,366 | 278 | $2,539 | 340 | $1,898 | - | $9,823 130,902 kWh |
$3,366 278 kW-months/year |
$2,539 340 MMBtu |
$1,898 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,109 Cost: $18,000 |
$5,185 | 69,033 | $267 | 22 | $657 | 88 | - | - | $5,185 69,033 kWh |
$267 22 kW-months/year |
$657 88 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |