Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2022 |
Principal Product | Cleaning uniforms, mats, and bulk products |
NAICS | 812332 - Industrial Launderers |
SIC | 7218 - Industrial Launderers |
Sales | $50,000,000-$100,000,000 |
# of Employees | 230 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 20,800,000 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $101,851 | 1,570,400 | kWh | $0.06 |
Electricity Demand | $75,080 | 4,513 | kW-months/year | $16.64 |
Electricity Fees | $17,040 | - | $ | - |
Natural Gas | $218,841 | 25,126 | MMBtu | $8.71 |
TOTAL ENERGY COSTS | $707,367 | |||
RECOMMENDED SAVINGS* | $112,226 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $58,911 Cost: $10,000 |
- | - | - | - | - | - | - | - | $58,911 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$58,911 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $24,436 Cost: $109,567 |
$31,225 | 481,120 | $16,174 | 972 | $(-18,152) | (-2,084) | $(-4,811) | - | - | - | - | - |
$31,225 481,120 kWh |
$16,174 972 kW-months/year |
$(-18,152) (-2,084) MMBtu |
$(-4,811) - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $12,034 Cost: $44,013 |
$12,034 | 185,142 | - | - | - | - | - | - | - | - | - | - |
$12,034 185,142 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $5,133 Cost: $6,000 |
$1,989 | 30,654 | - | - | $3,144 | 361 | - | - | - | - | - | - |
$1,989 30,654 kWh |
- - kW-months/year |
$3,144 361 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,821 Cost: $4,500 |
$3,821 | 58,874 | - | - | - | - | - | - | - | - | - | - |
$3,821 58,874 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,419 Cost: $2,740 |
$2,419 | 37,273 | - | - | - | - | - | - | - | - | - | - |
$2,419 37,273 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $2,188 Cost: $560 |
$2,058 | 31,716 | - | - | $130 | 15 | - | - | - | - | - | - |
$2,058 31,716 kWh |
- - kW-months/year |
$130 15 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,876 Cost: $2,748 |
- | - | - | - | $1,876 | 215 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,876 215 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $1,000 Cost: $25 |
- | - | - | - | - | - | - | - | - | - | $1,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
$1,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $408 Cost: $63 |
$408 | 6,290 | - | - | - | - | - | - | - | - | - | - |
$408 6,290 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $112,226 Cost: $180,216 |
$53,954 | 831,069 | $16,174 | 972 | $(-13,002) | (-1,493) | $(-4,811) | - | $58,911 | - | $1,000 | - | $53,954 831,069 kWh |
$16,174 972 kW-months/year |
$(-13,002) (-1,493) MMBtu |
$(-4,811) - $ |
$58,911 - $ |
$1,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost |