Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2023 |
Principal Product | Bread, Buns, and Rolls |
NAICS | 311812 - Commercial Bakeries |
SIC | 2051 - Bread, Cake, And Related Products |
Sales | $100,000,000-$500,000,000 |
# of Employees | 275 |
Plant Area (Sq.Ft.) | 120,000 |
Annual Production | 89,000,000 Pounds |
Production Hrs. Annual | 8,760 |
Location (State) | AR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $342,261 | 6,863,832 | kWh | $0.05 |
Electricity Demand | $181,065 | 12,457 | kW-months/year | $14.54 |
Natural Gas | $375,742 | 51,142 | MMBtu | $7.35 |
TOTAL ENERGY COSTS | $925,170 | |||
RECOMMENDED SAVINGS* | $130,344 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $51,041 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER |
Savings: $44,264 Cost: $3,287 |
$44,264 | 887,040 | - | - | - | - | - | - |
$44,264 887,040 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $41,378 Cost: $10,100 |
$41,378 | 829,216 | - | - | - | - | - | - |
$41,378 829,216 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.214 PURCHASE APPROPRIATELY SIZED MATERIAL |
Savings: $18,022 Cost: $87,000 |
- | - | - | - | $18,022 | 2,453 | - | - |
- - kWh |
- - kW-months/year |
$18,022 2,453 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $14,929 Cost: $45,390 |
- | - | - | - | $14,929 | 2,032 | - | - |
- - kWh |
- - kW-months/year |
$14,929 2,032 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $9,663 Cost: $1,500 |
$6,907 | 138,408 | $2,756 | 190 | - | - | - | - |
$6,907 138,408 kWh |
$2,756 190 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4112 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS |
Savings: $2,088 Cost: $4,500 |
$647 | 12,963 | - | - | - | - | $1,441 | - |
$647 12,963 kWh |
- - kW-months/year |
- - MMBtu |
$1,441 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $130,344 Cost: $151,777 |
$93,196 | 1,867,627 | $2,756 | 190 | $32,951 | 4,485 | $1,441 | - | $93,196 1,867,627 kWh |
$2,756 190 kW-months/year |
$32,951 4,485 MMBtu |
$1,441 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $51,041 Cost: $11,600 |
$48,285 | 967,624 | $2,756 | 190 | - | - | - | - | $48,285 967,624 kWh |
$2,756 190 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |