Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2024 |
Principal Product | Porcelain tile |
NAICS | 327120 - Clay Building Material and Refractories Manufacturing |
SIC | 3253 - Ceramic Wall And Floor Tile |
Sales | $10,000,000-$50,000,000 |
# of Employees | 178 |
Plant Area (Sq.Ft.) | 926,000 |
Annual Production | 3,650,000 Units |
Production Hrs. Annual | 8,760 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,249,965 | 16,408,800 | kWh | $0.08 |
Electricity Demand | $634,909 | 43,870 | kW-months/year | $14.47 |
Electricity Fees | $(-297,376) | - | $ | - |
Natural Gas | $834,616 | 259,600 | MMBtu | $3.22 |
TOTAL ENERGY COSTS | $2,570,482 | |||
RECOMMENDED SAVINGS* | $1,659,354 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $1,156,718 Cost: $75,000 |
- | - | - | - | $1,156,718 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,156,718 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $259,778 Cost: $1,375,785 |
$259,778 | 3,382,521 | - | - | - | - | - | - | - | - | - | - |
$259,778 3,382,521 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $147,843 Cost: $200,000 |
- | - | - | - | $147,843 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$147,843 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4155 METER WASTE WATER |
Savings: $22,342 Cost: $10,000 |
- | - | - | - | - | - | - | - | $22,342 | 1,715 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$22,342 1,715 Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7225 CLOSE OUTDOOR AIR DAMPERS DURING WARM-UP / COOL-DOWN PERIODS |
Savings: $18,330 Cost: $3,200 |
- | - | - | - | - | - | - | - | - | - | $18,330 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
$18,330 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $17,400 Cost: $10,380 |
$13,828 | 180,057 | $3,572 | 247 | - | - | - | - | - | - | - | - |
$13,828 180,057 kWh |
$3,572 247 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $11,283 Cost: $30 |
- | - | - | - | - | - | $11,283 | 3,504 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$11,283 3,504 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $10,806 Cost: $12,000 |
$10,806 | 140,700 | - | - | - | - | - | - | - | - | - | - |
$10,806 140,700 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $7,504 Cost: $60 |
$7,504 | 97,709 | - | - | - | - | - | - | - | - | - | - |
$7,504 97,709 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $5,587 Cost: $1,500 |
- | - | - | - | - | - | $5,587 | 1,735 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$5,587 1,735 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,763 Cost: $1,345 |
$1,763 | 22,968 | - | - | - | - | - | - | - | - | - | - |
$1,763 22,968 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,659,354 Cost: $1,689,300 |
$293,679 | 3,823,955 | $3,572 | 247 | $1,304,561 | - | $16,870 | 5,239 | $22,342 | 1,715 | $18,330 | - | $293,679 3,823,955 kWh |
$3,572 247 kW-months/year |
$1,304,561 - $ |
$16,870 5,239 MMBtu |
$22,342 1,715 Tgal |
$18,330 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Primary Product |