Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Alabama |
---|---|
Assessment Year | 2013 |
Principal Product | Cement |
NAICS | 327310 - Cement Manufacturing |
SIC | 3241 - Cement, Hydraulic |
Sales | $100,000,000-$500,000,000 |
# of Employees | 107 |
Plant Area (Sq.Ft.) | 4,300,000 |
Annual Production | 1,000,000 Tons |
Production Hrs. Annual | 8,760 |
Location (State) | AL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $7,284,777 | 112,073,496 | kWh | $0.06 |
TOTAL ENERGY COSTS | $7,284,777 | |||
RECOMMENDED SAVINGS* | $158,502 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $87,714 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $65,646 Cost: $30,000 |
$65,646 | 1,009,932 |
$65,646 1,009,932 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $29,047 Cost: $800 |
$29,047 | 446,885 |
$29,047 446,885 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $21,524 Cost: $800 |
$21,524 | 331,140 |
$21,524 331,140 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $20,585 Cost: $18,890 |
$20,585 | 316,680 |
$20,585 316,680 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $16,558 Cost: $27,390 |
$16,558 | 254,730 |
$16,558 254,730 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $5,142 Cost: $300 |
$5,142 | 79,112 |
$5,142 79,112 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $158,502 Cost: $78,180 |
$158,502 | 2,438,479 | $158,502 2,438,479 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $87,714 Cost: $47,880 |
$87,714 | 1,349,435 | $87,714 1,349,435 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Usage |