Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1989 |
Principal Product | MEDICAL INSTRUMENTS |
NAICS | n/a |
SIC | 3829 - Measuring & Controlling Devices, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 0 Units |
Production Hrs. Annual | 2,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $123,560 | 2,167,644 | kWh | $0.06 |
Natural Gas | $4,495 | 1,030 | MMBtu | $4.36 |
TOTAL ENERGY COSTS | $128,055 | |||
RECOMMENDED SAVINGS* | $15,247 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,505 |
#|Description |
Savings Cost |
Status | Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $10,742 Cost: $75,000 |
$1,742 | 19,050 | $9,000 | - |
$1,742 19,050 kWh |
$9,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $2,010 Cost: - |
$1,574 | 73,271 | $436 | - |
$1,574 73,271 kWh |
$436 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $2,495 Cost: $278 |
$2,295 | 41,911 | $200 | - |
$2,295 41,911 kWh |
$200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $15,247 Cost: $75,278 |
$5,611 | 134,232 | $9,636 | - | $5,611 134,232 kWh |
$9,636 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,505 Cost: $278 |
$3,869 | 115,182 | $636 | - | $3,869 115,182 kWh |
$636 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes |