Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1990 |
Principal Product | HAMBURGER BUNS |
NAICS | n/a |
SIC | 2051 - Bread, Cake, And Related Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 20,000,000 Pieces |
Production Hrs. Annual | 5,000 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $108,455 | 1,934,936 | kWh | $0.06 |
Natural Gas | $51,712 | 13,058 | MMBtu | $3.96 |
TOTAL ENERGY COSTS | $160,167 | |||
RECOMMENDED SAVINGS* | $6,957 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,428 |
#|Description |
Savings Cost |
Status | Natural Gas | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7314 REDUCE VENTILATION AIR |
Savings: $409 Cost: $1,000 |
$409 | 123 |
$409 123 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2492 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR |
Savings: $3,201 Cost: $3,000 |
$3,201 | 964 |
$3,201 964 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $2,019 Cost: - |
$2,019 | 608 |
$2,019 608 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS |
Savings: $1,328 Cost: $400 |
$1,328 | 400 |
$1,328 400 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $6,957 Cost: $4,400 |
$6,957 | 2,095 | $6,957 2,095 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,428 Cost: $1,000 |
$2,428 | 731 | $2,428 731 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Natural Gas | Natural Gas |